Sr. # |
Project Name |
Location |
Fuel / Technology |
Gross/ Installed Capacity |
Completion Year / Commercial Operation Date (COD) |
|
|
Residual Furnace Oil (RFO) |
||||||
|
1 |
Raiwind-Manga Road; Near Lahore |
RFO |
131 |
20.06.1997 |
||
|
2 |
Rawalpindi |
RFO |
165 |
17.03.2009 |
||
|
3 |
Near Lahore |
RFO |
200 |
09.06.2010 |
||
|
4 |
Near Lahore |
RFO |
200 |
21.07.2010 |
||
|
5 |
Near Faisalabad |
RFO |
200 |
13.01.2011 |
||
|
6 |
Narowal |
RFO |
220 |
22.04.2011 |
||
|
Sub Total (RFO) |
1,116 |
|
||||
|
Gas/RLNG |
||||||
|
7 |
Fateh Jang, Attock |
Gas/RLNG* |
31 |
06.06.2001(1st Phase) 20.09.2008(2nd Phase) |
||
|
8 |
Kabirwala, District Khanewal |
Gas/RLNG* |
157 |
21.10.1999 |
||
|
9 |
Daharki, Distt. Ghotki, Sindh |
Gas/RLNG* |
235 |
10.09.2001 |
||
|
10 |
Dera Murad Jamali, District Nasirabad, Balochistan |
Gas/RLNG* |
586 |
18.10.2000 |
||
|
11 |
Qadirpur, Sindh |
Gas/RLNG* |
227 |
27.03.2010 |
||
|
12 |
Sahiwal, Punjab |
Gas/RLNG* |
229 |
27.04.2010 |
||
|
13 |
Balloki, Punjab |
Gas/RLNG* |
229 |
24.05.2010 |
||
|
14 |
Muridke, Punjab |
Gas/RLNG* |
225 |
05.10.2010 |
||
|
15 |
Daharki, Sindh |
Gas/RLNG* |
185 |
16.05.2011 |
||
|
16 |
Bhikki, Punjab |
Gas/RLNG* |
225 |
25.06.2011 |
||
|
17 |
Dera Murad Jamali, Balochistan |
Gas/RLNG* |
404 |
04.04.2014 |
||
|
18 |
Jhang, Punjab |
Gas/RLNG |
10.5 |
13.07.2013 |
||
|
19 |
Haveli Bahadur Shah, Jhang |
RLNG |
1,230 |
09.05.2018 |
||
|
20 |
Balloki, Kasur, Punjab |
RLNG |
1,223 |
29.07.2018 |
||
|
21 |
Bhikki, Sheikhupura, Punjab |
RLNG |
1,180 |
19.05.2018 |
||
|
22 |
Near Trimmu Barrage, Jhang, Punjab |
RLNG |
1,263 |
23.06.2023 |
||
|
Sub Total (Gas/RLNG) |
7,639.5 |
|
||||
|
Hydel |
||||||
|
23 |
7.5 km Downstream Mangla Dam, Azad Jammu & Kashmir |
Hydel |
84 |
23.03.2013 |
||
|
24 |
Kunhar River, KP/AJ&K |
Hydel |
147 |
08.11.2017 |
||
|
25 |
Poonch River, Gulpur, AJ&K |
Hydel |
102 |
10.03.2020 |
||
|
26 |
Jehlum River, Distt. Rawalpindi, Punjab |
Hydel |
720 |
29.06.2022 |
||
|
27 |
Kunhar River, Mansehra, KP |
Hydel |
884 |
14.09.2024 |
||
|
Sub Total (Hydel) |
1,937 |
|
||||
|
Imported Coal |
||||||
|
28 |
Qadarabad, Sahiwal, Punjab |
Imported Coal |
1,320 |
28.10.2017 |
||
|
29 |
Port Qasim, Karachi, Sindh |
Imported Coal |
1,320 |
25.04.2018 |
||
|
30 |
Hub, Balochistan |
Imported Coal |
1,320 |
17.08.2019 |
||
|
Sub Total (Imported Coal) |
3,960 |
|
||||
|
Thar Coal |
||||||
|
31 |
Thar Block-II, Sindh |
Thar Coal |
660 |
10.07.2019 |
||
|
32 |
Port Qasim, Sindh |
Thar Coal |
660 |
21.03.2022 |
||
|
33 |
Thar Block-II, Sindh |
Thar Coal |
330 |
01.10.2022 |
||
|
34 |
Thar Block-I, Sindh |
Thar Coal |
1,320 |
05.02.2023 |
||
|
35 |
Thar Block-II, Sindh |
Thar Coal |
330 |
17.02.2023 |
||
|
Sub Total (Thar Coal) |
3,300 |
|
||||
|
Bagasse |
||||||
|
36 |
Rahim Yar Khan, Punjab |
Bagasse |
26.35 |
12-Jun-14 |
||
|
37 |
Ghotki, Sindh |
Bagasse |
26.35 |
3-Oct-14 |
||
|
38 |
Chiniot, Punjab |
Bagasse |
62.4 |
28-Nov-15 |
||
|
39 |
Rahim Yar Khan, Punjab |
Bagasse |
30 |
24-Mar-15 |
||
|
40 |
Rahim Yar Khan, Punjab |
Bagasse |
15 |
10-Mar-17 |
||
|
41 |
Layyah, Punjab |
Bagasse |
41 |
1-Dec-17 |
||
|
42 |
Mianwali, Punjab |
Bagasse |
36 |
4-Jan-19 |
||
|
43 |
Faisalabad, Punjab |
Bagasse |
22 |
15-Feb-19 |
||
|
44 |
Mandi Baha-ud-Din, Punjab |
Bagasse |
32 |
10-Oct-25 |
||
|
Sub Total (Bagasse) |
291.1 |
|
||||
|
Solar PV |
||||||
|
45 |
Quaid-e-Azam Solar Power Park near Bahawalpur |
Solar PV |
100 |
31-Jul-16 |
||
|
46 |
Quaid-e-Azam Solar Power Park near Bahawalpur |
Solar PV |
100 |
31-May-16 |
||
|
47 |
Quaid-e-Azam Solar Power Park near Bahawalpur |
Solar PV |
100 |
31-Jul-16 |
||
|
48 |
Bahawalpur, Punjab |
Solar PV |
100 |
15-Jul-15 |
||
|
49 |
Khushab, Punjab |
Solar PV |
12 |
13-Dec-17 |
||
|
50 |
Sahiwal, Punjab |
Solar PV |
18 |
14-Oct-17 |
||
|
51 |
Atlas Solar Limited (formerly Zhenfa Pakistan New Energy Company (Pvt.) Ltd. |
Layyah, Punjab |
Solar PV |
100 |
14-Apr-22 |
|
|
52 |
Sukkur, Sindh |
Solar PV |
50 |
10-Jan-24 |
||
|
53 |
Sukkur, Sindh |
Solar PV |
50 |
19-Jan-24 |
||
|
54 |
Sukkur, Sindh |
Solar PV |
50 |
01-Feb-24 |
||
|
Sub Total (Solar PV) |
680 |
|
||||
|
Wind |
||||||
|
55 |
Jhimpir, Sindh |
Wind |
49.5 |
16 May, 2013 |
||
|
56 |
Jhimpir, Sindh |
Wind |
56.4 |
26 Jul, 2013 |
||
|
57 |
Jhimpir, Sindh |
Wind |
49.5 |
25 Nov, 2014 |
||
|
58 |
Gharo, Sindh |
Wind |
50 |
11 Apr, 2015 |
||
|
59 |
Gharo, Sindh |
Wind |
50 |
10 Dec, 2014 |
||
|
60 |
Jhimpir, Sindh |
Wind |
52.8 |
22 Nov, 2015 |
||
|
61 |
Jhimpir, Sindh |
Wind |
50 |
16 Sep, 2016 |
||
|
62 |
Jhimpir, Sindh |
Wind |
50 |
16 Sep, 2016 |
||
|
63 |
Jhimpir, Sindh |
Wind |
52.8 |
14 Oct, 2016 |
||
|
64 |
Act Wind (Pvt.) Ltd. (Formerly Tapal Wind Energy Pvt. Limited) |
Jhimpir, Sindh |
Wind |
30 |
7 Oct, 2016 |
|
|
65 |
Jhimpir, Sindh |
Wind |
50 |
18 Oct, 2016 |
||
|
66 |
Gharo, Sindh |
Wind |
49.5 |
11Oct, 2016 |
||
|
67 |
Gharo, Sindh |
Wind |
49.5 |
5 Apr, 2017 |
||
|
68 |
Jhimpir, Sindh |
Wind |
49.5 |
18 Apr, 2017 |
||
|
69 |
Jhimpir, Sindh |
Wind |
99 |
16 Jun, 2017 |
||
|
70 |
Jhimpir, Sindh |
Wind |
49.735 |
16 Mar, 2018 |
||
|
71 |
Jhimpir, Sindh |
Wind |
49.735 |
15 Mar, 2018 |
||
|
72 |
Artistic Energy (Pvt.) Ltd. (Formerly Hartford Alternative Energy Pvt. Limited) |
Jhimpir , Sindh |
Wind |
49.3 |
16 Mar, 2018 |
|
|
73 |
Jhimpir, Sindh |
Wind |
49.5 |
30th Jun, 2018 |
||
|
74 |
Jhimpir, Sindh |
Wind |
49.5 |
9th Jul, 2018 |
||
|
75 |
Jhimpir, Sindh |
Wind |
49.735 |
16 Aug, 2018 |
||
|
76 |
Jhimpir, Sindh |
Wind |
49.735 |
14 Sep, 2018 |
||
|
77 |
Jhimpir, Sindh |
Wind |
49.735 |
11 Sep, 2018 |
||
|
78 |
Gharo, Sindh |
Wind |
50 |
27 Mar, 2019 |
||
|
79 |
Jhimpir, Sindh |
Wind |
50 |
14-Apr-22 |
||
|
80 |
Jhimpir, Sindh |
Wind |
50 |
16-Feb-22 |
||
|
81 |
Jhimpir, Sindh |
Wind |
50 |
9-Apr-22 |
||
|
82 |
Jhimpir, Sindh |
Wind |
50 |
25-Mar-22 |
||
|
83 |
Jamshoro, Sindh |
Wind |
50 |
20-Aug-21 |
||
|
84 |
Jhimpir, Sindh |
Wind |
50 |
27-Feb-22 |
||
|
85 |
Jhimpir, Sindh |
Wind |
50 |
27-May-22 |
||
|
86 |
Jhimpir, Sindh |
Wind |
60 |
6-Jun-22 |
||
|
87 |
Jhimpir, Sindh |
Wind |
50 |
2-May-22 |
||
|
88 |
Jhimpir, Sindh |
Wind |
50 |
27-Mar-22 |
||
|
89 |
Jhimpir, Sindh |
Wind |
50 |
7-Apr-22 |
||
|
90 |
Jhimpir, Sindh |
Wind |
50 |
1-Sep-21 |
||
|
Sub Total (Wind) |
1,845.47 |
|
||||
|
Grand Total |
20,769 |
|
||||
TRANSMISSION LINE PROJECT
| Sr. # | Project Name | Location | Technology | Load Transmitting Capacity (MW) | Year of Completion / Commercial Operation Date (COD) |
| 01 | Matiari-Lahore HVDC Transmission Line of 4000 MW load carrying capability (HVDC ±660 kV) | Matiari-Lahore | HVDC | 4,000 MW | 01.09.2021 |
* IPPs developed on indigenous gas but later allocated RLNG