Karot Hydropower Project

 

 

 

Salient Features

Project Company

Karot Power Company (Pvt.) Limited

Policy

Power Policy 2015

Category

Commissioned

Sub Category

CPEC

Main Sponsor

China Three Gorges South Asian Investment Limited - CSAIL

Main Sponsor Shareholder

99.84%

Other Sponsors

Focus Power Investment Limited

Other Sponsors Shareholder

0.16%

Lenders

Export-Import Bank of China, China Development Bank, Silk Road Fund, International Finance Corporation (IFC), HBL (Inter-Creditor Agent)

Province

AJK

Location

Dual Boundary of District Rawalpindi, Punjab & District Kotli, AJK

River

Jhelum River

Gross Capacity

720MW

Net Capacity

712.80MW

Technology

Hydro Electric

Configuration

1 x 4 Units (180) = 720 MW

Total Project Price (USD)

1698.26Million

Debt Equity Ratio

80:20

Debt Amount USD

1358.61Million

Equity Amount USD

339.65Million

Levelized Tariff

7.6152US c/kWh EPC Stage, 6.5/kWh (FS Stage)

Levelized CPP

7.3044US c/kWh

Levelized EPP

0.3108US c/kWh

1-10 Years Tariff

8.9708US c/kWh

11-30 Years Tariff

4.0032US c/kWh

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

30Years

Primary Fuel

Hydro

Fuel Supplier

N/A

EPC Contractor

(i) Yangtze Three Gorges Technology & Ecnomic Development Co. Ltd (ii) China Machinery Enginnering Coorporation - CMEC

Owner's Engineer

SMEC Australia

Net Efficiency

96% (Estimated)

Annual Availability

50.83%

Annual Energy Yields

3174GWh

 

 

 

Important Events

Submission of Proposal

30-AUG-2006

Approval of PPIB Board

08-FEB-2007

Issuance of Notice to Proceed

15-MAR-2007

Submission of PG@US$ 1000/MW

13-APR-2007

PG Validity

12-OCT-2009

Issuance of LOI

19-MAY-2007

Generation License Application

26-NOV-2013

Tariff Determination

27-APRIL-2016 11-DEC-2012 (FS)

Submission of PG@US$ 5000/MW

10-JUL-2013

Date of issuance of LOS

29-AUG-2013

Implementation Agreement

08-SEP-2016

Direct Implementation Agreement

15-DEC-2016

Power Purchase Agreement

30-AUG-2016

Water Use Agreement

28-SEP-2016 (AJK WUA), 25-OCT-2016 (Punjab WUA)

EPC Contract

09-FEB-2015

Financing Documents

15-DEC-2015

Achievement of Financial Close

22-FEB-2017

Partial Commissioning 1

28-MAY-2021

RCOD

22-AUG-2022 237 days extension in RCOD was provided to the project from 28 Dec 2021 due to Covid-19. (Revised RCOD: 22nd AUG 2022)

Expected COD

02-AUG-2022

COD

29-JUN-2022 Commissioned