Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

ACT 2 Wind (Pvt.) Limited

 Salient Features

 

 

Project Company

ACT 2 Wind (Pvt.) Limited

Policy

RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Ahmed Muhammad

Main Sponsor Shareholder

20%

Other Sponsors

Mustafa Tapal, Adnaan Tapal, Danish Tapal, Asad Iqbal, Perwaiz Khurshid Akhtar, Abdullah Akhtar, Javed Akhtar, Farooq Javed, Mansoor Akhtar, Zeeshan Mansoor, Zain Mansoor, Jahangir Akhtar Bilal Jahangir

Other Sponsors Shareholder

80% 7.73333333333333%, 3.86666666666667%, 0.0333333333333333%, 1.16666666666667%, 1.16666666666667%, 1.76666666666667%, 1.73333333333333%, 1.16666666666667%, 1.16666666666667%, 1.16666666666667%, 1.76666666666667%, 1.73333333333333%,

Lenders

Lenders (Foreign): International Finance Corporation (IFC) Parallel Lender: Deutsche Investitions- und Entwicklungsgesellschaft - DEG (German Investment Corporation) Lenders (Local): Local Facility Financer: Bank Al Habib Ltd. Intercreditor Agent: Bank Al Habib Ltd. Commercial Facility Agent: Bank Al Habib Ltd. Offshore Account Bank: NBP Onshore Accoun Bank: Bank Al Habib Ltd. Offshore Security Trustee: Bank Al Habib Behrain Onshore Security Trustee: Bank Al Habib Ltd.

Province

Sindh

Location

Jhimpir

Gross Capacity

50MW

Net Capacity

47.7MW

Configuration

20 x 2.5MW (Gold Wind GW-121) WTG

Total Project Price (USD)

62.952Million

Debt Equity Ratio

80:20

Debt Amount USD

50.3616Million

Equity Amount USD

12.5904Million

Levelized Tariff

12.5904US c/kWh Exchange Rates 120 PKR/USD

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

25Years

EPC Contractor

Power China Huadong

Owner's Engineer

Hydrochina International Engineering Company Limited

Net Efficiency

37.1% Net Capacity Factor: 37.1 %

 Important Events

 

 

Issuance of LOI

20-OCT-2015

Tariff Determination

19-NOV-2018

Date of issuance of LOS

07-NOV-2019

Implementation Agreement

12-NOV-2019 GOP Guarantee 18-Nov-2019

Power Purchase Agreement

11-NOV-2019 EPA

Direct Power Purchase Agreement

14-NOV-2019 Direct EPA

Achievement of Financial Close

18-NOV-2019

COD

27-FEB-2022