Private Power & Infrastructure Board |
||
|
ACT 2 Wind (Pvt.) Limited |
||
|
Salient Features |
|
|
|
Project Company |
ACT 2 Wind (Pvt.) Limited |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Ahmed Muhammad |
|
|
Main Sponsor Shareholder |
20% |
|
|
Other Sponsors |
Mustafa Tapal, Adnaan Tapal, Danish Tapal, Asad Iqbal, Perwaiz Khurshid Akhtar, Abdullah Akhtar, Javed Akhtar, Farooq Javed, Mansoor Akhtar, Zeeshan Mansoor, Zain Mansoor, Jahangir Akhtar Bilal Jahangir |
|
|
Other Sponsors Shareholder |
80% 7.73333333333333%, 3.86666666666667%, 0.0333333333333333%, 1.16666666666667%, 1.16666666666667%, 1.76666666666667%, 1.73333333333333%, 1.16666666666667%, 1.16666666666667%, 1.16666666666667%, 1.76666666666667%, 1.73333333333333%, |
|
|
Lenders |
Lenders (Foreign): International Finance Corporation (IFC) Parallel Lender: Deutsche Investitions- und Entwicklungsgesellschaft - DEG (German Investment Corporation) Lenders (Local): Local Facility Financer: Bank Al Habib Ltd. Intercreditor Agent: Bank Al Habib Ltd. Commercial Facility Agent: Bank Al Habib Ltd. Offshore Account Bank: NBP Onshore Accoun Bank: Bank Al Habib Ltd. Offshore Security Trustee: Bank Al Habib Behrain Onshore Security Trustee: Bank Al Habib Ltd. |
|
|
Province |
Sindh |
|
|
Location |
Jhimpir |
|
|
Gross Capacity |
50MW |
|
|
Net Capacity |
47.7MW |
|
|
Configuration |
20 x 2.5MW (Gold Wind GW-121) WTG |
|
|
Total Project Price (USD) |
62.952Million |
|
|
Debt Equity Ratio |
80:20 |
|
|
Debt Amount USD |
50.3616Million |
|
|
Equity Amount USD |
12.5904Million |
|
|
Levelized Tariff |
12.5904US c/kWh Exchange Rates 120 PKR/USD |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
25Years |
|
|
EPC Contractor |
Power China Huadong |
|
|
Owner's Engineer |
Hydrochina International Engineering Company Limited |
|
|
Net Efficiency |
37.1% Net Capacity Factor: 37.1 % |
|
|
Important Events |
|
|
|
Issuance of LOI |
20-OCT-2015 |
|
|
Tariff Determination |
19-NOV-2018 |
|
|
Date of issuance of LOS |
07-NOV-2019 |
|
|
Implementation Agreement |
12-NOV-2019 GOP Guarantee 18-Nov-2019 |
|
|
Power Purchase Agreement |
11-NOV-2019 EPA |
|
|
Direct Power Purchase Agreement |
14-NOV-2019 Direct EPA |
|
|
Achievement of Financial Close |
18-NOV-2019 |
|
|
COD |
27-FEB-2022 |
|
|
|
|
|