Private Power & Infrastructure Board |
||
|
UEP Wind Power (Pvt.) Limited |
||
|
Salient Features |
|
|
|
Project Company |
UEP Wind Power (Pvt.) Limited |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Super Success Investments Limited |
|
|
Main Sponsor Shareholder |
100% |
|
|
Lenders |
Lenders (Foreign): China Development Bank |
|
|
Province |
Sindh |
|
|
Location |
Jhimpir, Thatta, Sindh |
|
|
Gross Capacity |
99MW |
|
|
Net Capacity |
96.68MW |
|
|
Configuration |
66 x 1.5 MW (Gold Wind- GW 77) WTG |
|
|
Total Project Price (USD) |
243.42Million |
|
|
Debt Equity Ratio |
75:25 |
|
|
Debt Amount USD |
182.565Million |
|
|
Equity Amount USD |
60.855Million |
|
|
Levelized Tariff |
13.5244US c/kWh Reference Exchange Rates 97.6 PKR/USD |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
20Years |
|
|
EPC Contractor |
China Ghazouba Group Company |
|
|
Owner's Engineer |
Goldwind Pakistan (Private) Limited |
|
|
Net Efficiency |
31% Net Capacity Factor 31% |
|
|
Important Events |
|
|
|
Issuance of LOI |
15-NOV-2011 |
|
|
Tariff Determination |
13-DEC-2013 |
|
|
Date of issuance of LOS |
05-MAR-2014 |
|
|
Implementation Agreement |
06-FEB-2015 GOP Guarantee: 30-MAR-2015 1st IA Amendment: 01-JUN-2017 |
|
|
Power Purchase Agreement |
20-DEC-2014 EPA EPA Amendment 23-MAY-2017 Supplemental Agreement 12-Jan-2018 |
|
|
Achievement of Financial Close |
17-DEC-2015 |
|
|
COD |
16-JUN-2017 |
|