Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

Master Wind Energy (Pvt.) Limited

 Salient Features

 

 

Project Company

Master Wind Energy (Pvt.) Limited

Policy

RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Nadeem Malik

Main Sponsor Shareholder

23.3%

Other Sponsors

Najeeb Malik, Shahzad Malik, NM Holding (Pvt.) Limited, Najeeb Holding (Pvt.) Limited, Master Textiles Mills Limited, Procon Engineering (Pvt.) Limited.

Other Sponsors Shareholder

77.7% 6%, 7%, 16.3%, 17.3%, 15%, 15%,

Lenders

Lenders (Foreign): Overseas Private Investment Corporation, an agency of the United States of America. Lenders (Local): Meezan Bank Ltd. Bank Al-Habib Ltd, The Bank of Punjab & Habib Metropolitan Bank Ltd.

Province

Sindh

Location

Jhimpir District Thattha , Sindh

Gross Capacity

49.5MW

Net Capacity

47.7MW

Configuration

33 x 1.6 MW (GE 1.6-82.5) WTG

Total Project Price (USD)

126.99Million

Debt Equity Ratio

75:25

Debt Amount USD

95.2425Million

Equity Amount USD

31.7475Million

Levelized Tariff

15.1088US c/kWh Reference Exchange Rates 97.6 PKR/USD

Power Purchaser

National Transmission and Despatch Company (NTDC)

Term of Project

20Years

EPC Contractor

Zhenjiang Engineering Science & Technology Development Co. Ltd.

Owner's Engineer

General Electric International Inc

Net Efficiency

32.8% Net Capacity Factor 32.8%

 Important Events

 

 

Issuance of LOI

26-JAN-2005

Tariff Determination

23-APR-2014

Date of issuance of LOS

08-AUG-2012

Implementation Agreement

12-JAN-2015 GOP Guarantee 27-March 2015

Direct Implementation Agreement

20-MAR-2015

Power Purchase Agreement

16-JAN-2019 EPA

Direct Power Purchase Agreement

19-MAR-2015 Direct EPA

Expected Financial Close

09-FEB-2015

COD

14-OCT-2016