Private Power & Infrastructure
Board |
||
|
330MW Thar Lignite Coal Based Power Project by ThalNova Power Thar(Private) Ltd |
||
|
Salient Features |
|
|
|
Project Company |
Thal Nova Power Thar (Pvt.) Limited |
|
|
Sub Category |
CPEC |
|
|
Main Sponsor |
Thal Power Private Limited |
|
|
Other Sponsors |
Novatex Limited & Descon Engineerring Limited |
|
|
Province |
Sindh |
|
|
Location |
Thar Block-II Sindh |
|
|
Gross Capacity |
330MW |
|
|
Net Capacity |
300.30MW |
|
|
Technology |
Sub-Critical System Turbines |
|
|
Configuration |
1 X 330 |
|
|
Total Project Price (USD) |
497.7Million |
|
|
Debt Amount USD |
373.27Million |
|
|
Equity Amount USD |
124.43Million |
|
|
Levelized Tariff |
8.5015US c/kWh |
|
|
Levelized CPP |
6.3750US c/kWh |
|
|
Levelized EPP |
2.1265US c/kWh |
|
|
1-10 Years Tariff |
9.8574US c/kWh |
|
|
11-30 Years Tariff |
6.2903US c/kWh |
|
|
Power Purchaser |
CPPA-GL |
|
|
Term of Project |
30Years |
|
|
Primary Fuel |
Thar Coal |
|
|
Fuel Supplier |
SECMC |
|
|
Important Events |
|
|
|
Issuance of LOI |
02-AUG-2016 |
|
|
Generation License Application |
24-JAN-2017 |
|
|
Tariff Determination |
18-OCT-2016 |
|
|
Date of issuance of LOS |
08-DEC-2016 |
|
|
LOS Extension 1 |
02-AUG-2017 |
|
|
LOS Extension 2 |
20-Jun-2018 |
|
|
LOS Extension 3 |
14-Dec-2018 |
|
|
LOS Extension 4 |
31-Oct-2019 |
|
|
LOS Extension 5 |
06-Feb-2020 |
|
|
LOS Extension 6 |
28-July-2020 |
|
|
Implementation Agreement |
24-NOV-2017 |
|
|
Power Purchase Agreement |
21-JULY-2017 |
|
|
Fuel Supply Agreement |
13-MAY-2017 |
|
|
Achievement of Financial Close |
30-September-2020 |
|
|
Expected COD |
31-MAR-2021 |
|
|
|
COD |
17-FEB-2023 |