Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

Harappa Solar (Pvt.) Limited

 Salient Features

 

 

Project Company

Harappa Solar (Pvt.) Limited

Policy

RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Rana Nasim Ahmed

Main Sponsor Shareholder

75%

Other Sponsors Shareholder

25% Windforce PLC, Sri Lanka 13% Mohammad Khaqan Babar Cheema 12%

Lenders

i. The Bank of Punjab ii. Askari Bank Limited iii. Eco Trade and Development Bank iv. Pak-Oman Investment Company Limited.

Province

Punjab

Location

Harappa, Sahiwal

Gross Capacity

18MW

Total Project Price (USD)

23.43Million

Debt Equity Ratio

75:25

Levelized Tariff

11.6972US c/kWh

1-10 Years Tariff

14.3961US c/kWh 14.3961 US Cents/kWh 15.1159 PKR/kWh

11-25 Years Tariff

6.0422US c/kWh 6.0422 US Cents/kWh 6.3443 PKR / kWh

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

25Years

EPC Contractor

Sunec

Owner's Engineer

&M Solutions (OMS)

Net Efficiency

17.22%

 Important Events

 

 

Issuance of LOI

31-DEC-2014

Tariff Determination

02-JUL-2015 2-JUL-2015 (Original) 26-FEB-2016 (Revised) 20-NOV-2018 (COD)

Date of issuance of LOS

23-SEP-2015

Implementation Agreement

06-JUN-2016

Direct Implementation Agreement

15-FEB-2017

Power Purchase Agreement

30-APR-2016 EPA

Direct Power Purchase Agreement

15-FEB-2017 Direct EPA

Achievement of Financial Close

23-FEB-2017

COD

14-OCT-2017