FAUJI KABIRWALA POWER PROJECT |
Salient Features |
| Company |
Fauji Kabirwala Power Company Limited |
| Capacity |
157 MW (Gross) |
| Location |
Kabirwala, District Khanewal |
| Fuel |
Low BTU Gas + Pipeline Quality Gas |
| Technology |
Combined Cycle + Steam Turbines |
| Plant Configuration |
2 Gas Turbines of 48.4 MW each and a Steam Turbine of capacity 59.4 MW |
| Power Purchaser |
WAPDA |
| Fuel Supplier |
OGDC |
| Term of the PPA |
30 Years |
| Registered Address |
Fauji Kabirwala Power Co. Ltd. 14 Harley Street Rawalpindi Cantt |
| Email |
[email protected] |
Important Milestones |
| Submission of Application |
April 28, 1994 |
| Issuance of Letter of Interest (LOI) |
May 19, 1994 |
| Issuance of Letter of Support (LOS) |
June 30, 1994 |
| Date of Financial Closing |
June 2, 1996 |
| Commissioning Date |
October 21, 1999 |
| Net / Dependable Capacity |
151 MW |
Contractual Agreements |
| Implementation Agreement |
September 24, 1994 |
| Amendment No. 1 |
January 28, 1996 |
| Power Purchase Agreement (PPA) |
January 12, 1995 |
| Amendment No. 1 |
January 25, 1996 |
| GOP Guarantee |
July 23, 1996 |