Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

Artistic Wind Power (Pvt.) Limited

 Salient Features

 

 

Project Company

Artistic Wind Power (Pvt.) Limited.

Policy

RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Artistic Milliners (Private) Limited

Main Sponsor Shareholder

100%

Other Sponsors Shareholder

0%

Lenders

Lenders (Foreign): International Finance Corporation, USA Lenders (Local): Lenders (Local) Local Facility Financer: Bank Al Habib Ltd. Meezan Bank Ltd. Intercreditor Agent: Bank Al Habib Ltd. Offshore Account Bank: United National Bank Limited (trading as UBL UK) Onshore Account Bank: Bank Al Habib Ltd. Offshore Security Trustee: Bank Al Habib Ltd. Bahrain Onshore Security Trustee: Bank Al Habib Ltd. Musharaka Agent: Meezan Bank Ltd.

Province

Sindh

Location

Jhimpir

Gross Capacity

50MW

Net Capacity

47.9MW

Configuration

20 x 2.5MW (Gold Wind GW-121) WTG

Total Project Price (USD)

62.952Million

Debt Equity Ratio

80.20

Debt Amount USD

50.3616Million

Equity Amount USD

12.5904Million

Levelized Tariff

4.7212US c/kWh Reference Exchange Rate 120 PKR/USD

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

25Years

EPC Contractor

Power China huadong

Owner's Engineer

HydroChina International Engineering Company Limited, Pakistan

Net Efficiency

37.5% Net Capacity Factor 37.5%

 Important Events

 

 

Issuance of LOI

15-SEP-2015

Tariff Determination

19-NOV-2018

Date of issuance of LOS

08-NOV-2019

Implementation Agreement

12-NOV-2019 26-DEC-2016

Direct Implementation Agreement

15-NOV2019

Power Purchase Agreement

11-NOV-2019 EPA

Direct Power Purchase Agreement

14-NOV-2019 Direct EPA

Achievement of Financial Close

08-NOV-2019

COD

16-FEB-2022