Private Power & Infrastructure Board |
||
|
Artistic Wind Power (Pvt.) Limited |
||
|
Salient Features |
|
|
|
Project Company |
Artistic Wind Power (Pvt.) Limited. |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Artistic Milliners (Private) Limited |
|
|
Main Sponsor Shareholder |
100% |
|
|
Other Sponsors Shareholder |
0% |
|
|
Lenders |
Lenders (Foreign): International Finance Corporation, USA Lenders (Local): Lenders (Local) Local Facility Financer: Bank Al Habib Ltd. Meezan Bank Ltd. Intercreditor Agent: Bank Al Habib Ltd. Offshore Account Bank: United National Bank Limited (trading as UBL UK) Onshore Account Bank: Bank Al Habib Ltd. Offshore Security Trustee: Bank Al Habib Ltd. Bahrain Onshore Security Trustee: Bank Al Habib Ltd. Musharaka Agent: Meezan Bank Ltd. |
|
|
Province |
Sindh |
|
|
Location |
Jhimpir |
|
|
Gross Capacity |
50MW |
|
|
Net Capacity |
47.9MW |
|
|
Configuration |
20 x 2.5MW (Gold Wind GW-121) WTG |
|
|
Total Project Price (USD) |
62.952Million |
|
|
Debt Equity Ratio |
80.20 |
|
|
Debt Amount USD |
50.3616Million |
|
|
Equity Amount USD |
12.5904Million |
|
|
Levelized Tariff |
4.7212US c/kWh Reference Exchange Rate 120 PKR/USD |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
25Years |
|
|
EPC Contractor |
Power China huadong |
|
|
Owner's Engineer |
HydroChina International Engineering Company Limited, Pakistan |
|
|
Net Efficiency |
37.5% Net Capacity Factor 37.5% |
|
|
Important Events |
|
|
|
Issuance of LOI |
15-SEP-2015 |
|
|
Tariff Determination |
19-NOV-2018 |
|
|
Date of issuance of LOS |
08-NOV-2019 |
|
|
Implementation Agreement |
12-NOV-2019 26-DEC-2016 |
|
|
Direct Implementation Agreement |
15-NOV2019 |
|
|
Power Purchase Agreement |
11-NOV-2019 EPA |
|
|
Direct Power Purchase Agreement |
14-NOV-2019 Direct EPA |
|
|
Achievement of Financial Close |
08-NOV-2019 |
|
|
COD |
16-FEB-2022 |
|