Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

1320 MW Thar Coal Power Project by Shanghai Electric

 Salient Features

 

 

Project Company

Thar Coal Block-I Power Generation Co. Ltd.

Sub Category

CPEC

Main Sponsor

Shanghai Electric (Group) Corporation

Province

Sindh

Location

Thar Block-I Sindh

Gross Capacity

1320MW 660 X 2

Net Capacity

1214MW 607 X 2

Configuration

660 X 2

Total Project Price (USD)

1912.2Million

Debt Amount USD

1434.15Million

Levelized Tariff

8.3341US c/kWh

Power Purchaser

CPPA-GL

Term of Project

30Years

Primary Fuel

Thar Coal

Fuel Supplier

Sino-Sindh Resources Ltd.

 Important Events

 

 

Issuance of LOI

21-AUG-2015

LOI Extension 1

01-MAR-2016

Generation License Application

29-DEC-2016

Tariff Determination

10-JUN-2016

Date of issuance of LOS

20-JUL-2016

LOS Extension 1

16-SEP-2017

LOS Extension 2

12-JAN-2018 PPIB Board has approved a third amendment to the LOS with FC date till 20-OCT-2018

LOS Extension 3

17-Aug-2018

LOS Extension 4

22-Feb-2019

LOS Extension 5

10-July-2019

LOS Extension 6

10-Dec-2019

LOS Extension 7

19-Mar-2020

LOS Extension 8

10-July-2020

LOS Extension 9

24-Feb-2021

LOS Extension 10

24-Aug-2021

Achievement of Financial Close

31-Dec-2021

Expected COD

31-May-2022

 

COD

05-Feb-2023