Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

Tenaga Generasi Limited

 Salient Features

 

 

Project Company

Tenaga Generasi Limited

Policy

RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Artistic Milliners (Private) Limited

Main Sponsor Shareholder

100%

Lenders

Lenders (Foreign) International Finance Corporation (IFC) Overseas Private Investment Corporation an agency of the United States of America Lenders (Local) Commercial Facility Financier: HBL & Soneri Bank Ltd. Commercial Facility Arranger: HBL Commercial Facility Agent: HBL Intercreditor Agent: Citi Bank International Ltd. LCY Issuing Bank: Bank Al Habib Ltd. Onshore Security Trustee: Citi Bank N.A. Karachi branch Offshore Security Trustee: Citi Bank N.A London Onshore Account Bank: Citi Bank N.A Karachi Offshore Account Bank: Citi Bank N.A. acting through its London branch

Province

Sindh

Location

Gharo, Sindh

Gross Capacity

49.5MW

Net Capacity

47.2MW

Configuration

30 x 1.6 MW (GE 1.6-xle) & 1 x1.5 MW (GE 1.5-xle) WTG

Total Project Price (USD)

124.96Million

Debt Equity Ratio

75:25

Debt Amount USD

93.72Million

Equity Amount USD

31.24Million

Levelized Tariff

14.3166US c/kWh 97.6

Term of Project

20Years

EPC Contractor

China Machinery Engineering Corporation

Owner's Engineer

Engro Energy Services Limited

 Important Events

 

 

Issuance of LOI

20-SEP-2004

Tariff Determination

23-APR-2014

Date of issuance of LOS

04-SEP-2012

Implementation Agreement

27-JAN-2015 (GOP) Guarantee 27-MAR-2015

Direct Implementation Agreement

25-MAR-2015

Power Purchase Agreement

29-DEC-2014 EPA

Direct Power Purchase Agreement

31-MAR-2015 Direct EPA

Achievement of Financial Close

27-MAR-2015

COD

11-OCT-2016