LIBERTY DAHARKI POWER PROJECT |
Salient Features |
| Company |
Liberty Daharki Power Limited |
| Capacity |
235 MW (Gross) |
| Location |
Daharki, District Ghotki, Sindh |
| Fuel |
Natural Gas |
| Technology |
Combined Cycle |
| Plant Configuration |
One Gas Turbine + One Steam Turbine + One Heat Recovery Steam Generator |
| Power Purchaser |
WAPDA |
| Fuel Supplier |
SNGPL |
| Term of the PPA |
25 Years |
| Registered Address |
Liberty Power Limited 90 Razia Sharif Plaza 4th Floor, Blue Area Islamabad. |
| Email |
[email protected] |
Important Milestones |
| Submission of Application |
March 26, 1994 |
| Issuance of Letter of Interest (LOI) |
July 6, 1995 |
| Issuance of Letter of Support (LOS) |
July 17, 1995 |
| Date of Financial Closing |
July 21, 1996 |
| Commissioning Date |
September 10, 2001 |
| Net / Dependable Capacity |
211 MW |
Contractual Agreements |
| Implementation Agreement (IA) |
November 22, 1995 |
| Power Purchase Agreement (PPA) |
November 26, 1995 |
| Fuel Supply Agreement (FSA) |
September 1, 2000 |