Salient Features |
| Company |
Huaneng Shandong Ruyi (Pak) Energy (Pvt) Ltd |
| Capacity |
1320 MW (Gross) |
| Location |
Qadarabad, Sahiwal |
| Fuel |
Imported Coal |
| Technology |
Super-Critical Steam Turbine |
| Plant Configuration |
2x660 |
| Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited |
| Term of the Project |
30 Years |
| Registered Address |
HNo 105, Street 10, Block H, Phase 5, DHA Lahore |
| Email |
[email protected] |
Important Milestones |
| LOI by Punjab Power Development Board: |
21st May 2014 |
| Approval of EIA by PEPA: |
28th May 2014 |
| Approval of application for acceptance of Upfront Tariff by NEPRA: |
31st March 2015 |
| Tripartite LOS by PPIB & PPDB: |
17th April 2015 |
| Generation License by NEPRA: |
10th June 2015 |
| Implementation Agreement: |
11th July 2015 |
| Power Purchase Agreement: |
11th July 2015 |
| Supplemental Agreement to Implementation Agreement: |
4th February 2016 |
| Financial Closing: |
23rd January 2017 |
| First Unit Inauguration: |
25th May 2017 |
| Second Unit Inauguration: |
3rd July 2017 |
| Commercial Operations Date: |
28th October 2017 |