SAHIWAL COAL POWER PROJECT |
Salient Features |
Company |
Huaneng Shandong Ruyi (Pak) Energy (Pvt) Ltd |
Capacity |
1320 MW (Gross) |
Location |
Qadarabad, Sahiwal |
Fuel |
Imported Coal |
Technology |
Super-Critical Steam Turbine |
Plant Configuration |
2x660 |
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited |
Term of the Project |
30 Years |
Registered Address |
HNo 105, Street 10, Block H, Phase 5, DHA Lahore |
Email |
huanengruy_energy@163.com |
Important Milestones |
LOI by Punjab Power Development Board: |
21st May 2014 |
Approval of EIA by PEPA: |
28th May 2014 |
Approval of application for acceptance of Upfront Tariff by NEPRA: |
31st March 2015 |
Tripartite LOS by PPIB & PPDB: |
17th April 2015 |
Generation License by NEPRA: |
10th June 2015 |
Implementation Agreement: |
11th July 2015 |
Power Purchase Agreement: |
11th July 2015 |
Supplemental Agreement to Implementation Agreement: |
4th February 2016 |
Financial Closing: |
23rd January 2017 |
First Unit Inauguration: |
25th May 2017 |
Second Unit Inauguration: |
3rd July 2017 |
Commercial Operations Date: |
28th October 2017 |