Lucky Electric Power Company Ltd |
||
|
Salient Features |
|
|
|
Project Company |
Lucky Electric Power Co. Ltd |
|
|
Policy |
Power Policy 2015 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Lucky Cement Limited |
|
|
Province |
Sindh |
|
|
Location |
Port Qasim, Karachi |
|
|
Gross Capacity |
660MW |
|
|
Net Capacity |
607MW |
|
|
Technology |
Super-Critical Steam Turbine |
|
|
Configuration |
1 x 660 MW |
|
|
Total Project Price (USD) |
1080.9Million |
|
|
Debt Equity Ratio |
75:25 |
|
|
Debt Amount USD |
810.675Million |
|
|
Equity Amount USD |
270.225Million |
|
|
Levelized Tariff |
9.2100US c/kWh |
|
|
Levelized CPP |
4.6778US c/kWh |
|
|
Levelized EPP |
4.5322US c/kWh |
|
|
1-10 Years Tariff |
10.4454US c/kWh |
|
|
11-25 Years Tariff |
6.8974US c/kWh |
|
|
Power Purchaser |
CPPAGL |
|
|
Term of Project |
30Years |
|
|
Primary Fuel |
Thar Coal |
|
|
Fuel Supplier |
SECMC |
|
|
EPC Contractor |
SEPCOIII |
|
|
Net Efficiency |
39% |
|
|
Annual Availability |
85% |
|
|
Annual Energy Yields |
4519GWh |
|
|
Important Events |
|
|
|
Submission of Proposal |
29-Sep-2014 |
|
|
Approval of PPIB Board |
02-JUL-2014 |
|
|
Issuance of Notice to Proceed |
15-JAN-2015 |
|
|
Submission of PG@US$ 1000/MW |
27-JAN-2015 |
|
|
PG Validity |
19-NOV-2015 |
|
|
Issuance of LOI |
11-FEB-2015 |
|
|
Generation License Application |
03-MAR-2016 |
|
|
Tariff Determination |
20-OCT-2016 |
|
|
Submission of PG@US$ 5000/MW |
06-APR-2015 |
|
|
Date of issuance of LOS |
08-JUN-2015 |
|
|
LOS Extension 1 |
26-Sep-2016 |
|
|
LOS Extension 2 |
09-Jan-2018 |
|
|
Implementation Agreement |
08-Mar-2018 |
|
|
Direct Implementation Agreement |
22-Jun-2018 |
|
|
Power Purchase Agreement |
07-Mar-2018 |
|
|
EPC Contract |
23-Dec-2016 |
|
|
Achievement of Financial Close |
25-June-2018 |
|
|
RCOD |
1-Mar-2021 |
|
|
|
COD |
21-Mar-2022 |