Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

1263 MW RLNG Power Project by PTPL

 Salient Features

 

 

Project Company

Punjab Thermal Power (Pvt.) Limited (PTPL)

Policy

Power Policy 2015

Category

Commissioned

Main Sponsor

Govt. of Punjab

Main Sponsor Shareholder

100%

Province

Punjab

Location

Near Trimmu Barrage, District Jhang, Punjab

Gross Capacity

1263.2MW

Net Capacity

1242.7MW

Technology

Combined Cycle Gas Turbine (H - Class GT Siemens - SGT5-8000H

Configuration

2GT+2HRSG+1ST

Total Project Price (USD)

801.84Million

Debt Equity Ratio

75:25

Levelized Tariff

6.5374US c/kWh

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

30Years

Primary Fuel

RLNG

Secondary Fuel

HSD

Fuel Supplier

SNGPL

EPC Contractor

China Machinery Engineering Corporatoin (CMEC)

Net Efficiency

61.16%

Annual Availability

92%

 Important Events

 

 

Submission of Proposal

12-JUN-2017

Issuance of Notice to Proceed

14-JUL-2017

Issuance of LOI

26-JUL-2017

Generation License Application

26-JUL-2017

Tariff Determination

26-DEC-2017

Date of issuance of LOS

26-JAN-2018

LOS Extension 1

16-FEB-2018

LOS Extension 2

11-DEC-2018

LOS Extension 3

17-JUL-2019

LOS Extension 4

22-JAN-2020

LOS Extension 5

2-FEB-2021

Achievement of Financial Close

23-APR-2021

Partial Commissioning 1

27-JUL-2022

Partial Commissioning 2

3-AUG-2022

COD

23-JUN-2023