Private Power & Infrastructure
Board |
||
|
1263 MW RLNG Power Project by PTPL |
||
|
Salient Features |
|
|
|
Project Company |
Punjab Thermal Power (Pvt.) Limited (PTPL) |
|
|
Policy |
Power Policy 2015 |
|
|
Category |
Commissioned |
|
|
Main Sponsor |
Govt. of Punjab |
|
|
Main Sponsor Shareholder |
100% |
|
|
Province |
Punjab |
|
|
Location |
Near Trimmu Barrage, District Jhang, Punjab |
|
|
Gross Capacity |
1263.2MW |
|
|
Net Capacity |
1242.7MW |
|
|
Technology |
Combined Cycle Gas Turbine (H - Class GT Siemens - SGT5-8000H |
|
|
Configuration |
2GT+2HRSG+1ST |
|
|
Total Project Price (USD) |
801.84Million |
|
|
Debt Equity Ratio |
75:25 |
|
|
Levelized Tariff |
6.5374US c/kWh |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
30Years |
|
|
Primary Fuel |
RLNG |
|
|
Secondary Fuel |
HSD |
|
|
Fuel Supplier |
SNGPL |
|
|
EPC Contractor |
China Machinery Engineering Corporatoin (CMEC) |
|
|
Net Efficiency |
61.16% |
|
|
Annual Availability |
92% |
|
|
Important Events |
|
|
|
Submission of Proposal |
12-JUN-2017 |
|
|
Issuance of Notice to Proceed |
14-JUL-2017 |
|
|
Issuance of LOI |
26-JUL-2017 |
|
|
Generation License Application |
26-JUL-2017 |
|
|
Tariff Determination |
26-DEC-2017 |
|
|
Date of issuance of LOS |
26-JAN-2018 |
|
|
LOS Extension 1 |
16-FEB-2018 |
|
|
LOS Extension 2 |
11-DEC-2018 |
|
|
LOS Extension 3 |
17-JUL-2019 |
|
|
LOS Extension 4 |
22-JAN-2020 |
|
|
LOS Extension 5 |
2-FEB-2021 |
|
|
Achievement of Financial Close |
23-APR-2021 |
|
|
Partial Commissioning 1 |
27-JUL-2022 |
|
|
Partial Commissioning 2 |
3-AUG-2022 |
|
|
COD |
23-JUN-2023 |
|