Private Power & Infrastructure Board |
||
|
Liberty Wind Power 2 (Pvt.) Limited |
||
|
Salient Features |
|
|
|
Project Company |
Liberty Wind Power 2 (Pvt.) Limited |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
100 |
|
|
Other Sponsors |
Mr. Azam Sakrani, Mr. Muhammad Ali, Mr. Muhammad Kashif |
|
|
Lenders |
Lenders (Foreign): CDC: CDC Group PLC, UK Lenders (Local): Original PKR Financers: HBL, Askari Bank Ltd and Soreri Bank Ltd Rupee Facility Agent: HBL Facility Agent: HBL Onshore Security Trustee: HBL Offshore Security Trustee: HBL Bank UK Limited Offshore Account Bank: HBL, UK Onshore Account Bank: HBL |
|
|
Province |
Sindh |
|
|
Location |
Jhimpir, Thatta |
|
|
Gross Capacity |
50MW |
|
|
Net Capacity |
47.9MW |
|
|
Configuration |
25 x 2.0 MW (Gamesa G-114) WTG |
|
|
Total Project Price (USD) |
63.906Million |
|
|
Debt Equity Ratio |
80:20 |
|
|
Debt Amount USD |
51.1248Million |
|
|
Equity Amount USD |
12.7812Million |
|
|
Levelized Tariff |
4.7824US c/kWh Reference Exchange Rate 120 PKR/USD |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
25Years |
|
|
EPC Contractor |
Power China huadong |
|
|
Owner's Engineer |
Hydrochina International Engineering Company Limited |
|
|
Annual Availability |
38% Net Capacity Factor 38% |
|
|
Important Events |
|
|
|
Issuance of LOI |
28-AUG-2015 |
|
|
Tariff Determination |
19-NOV-2018 |
|
|
Date of issuance of LOS |
08-NOV-2019 |
|
|
Implementation Agreement |
12-NOV-2019 Gop Guarantee 18-NOV-2019 |
|
|
Direct Implementation Agreement |
15-NOV-2019 |
|
|
Power Purchase Agreement |
11-NOV-2019 |
|
|
Direct Power Purchase Agreement |
14-NOV-2019 |
|
|
Achievement of Financial Close |
18-NOV-2019 |
|
|
COD |
27-MAY-2022 |
|