1320MW Coal Fired Project at HUB-Hub Power Company Ltd

 Salient Features

 

 

Project Company

China Power Hub Generation Company (Private) Limited

Sub Category

CPEC

Main Sponsor

Hub Power Company Limited

Other Sponsors

China Power International Holding

Province

Baluchistan

Location

Hub, Baluchistan

Gross Capacity

1320MW

Net Capacity

1214MW

Technology

Super-Critical Steam Turbine

Configuration

2X660

Total Project Price (USD)

1912.2Million

Levelized Tariff

8.3601US c/kWh

Levelized CPP

3.5039US c/kWh

Levelized EPP

4.8562US c/kWh

1-10 Years Tariff

9.0642US c/kWh

11-25 Years Tariff

7.0419US c/kWh

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited

Term of Project

30Years

Primary Fuel

Imported Coal

 Important Events

 

 

PG Validity

29-JUN-2016

Issuance of LOI

29-JUN-2015 1st extension to LOI: 17-Feb-2016

Generation License Application

26-AUG-2015

Tariff Determination

12-FEB-2016

Date of issuance of LOS

12-APR-2016 1st Amendment to LOS: 24-Jan-2017

LOS Extension 1

24-JAN-2017

LOS Extension 2

4-OCT-2017

Implementation Agreement

25-JAN-2017

Power Purchase Agreement

25-JAN-2017

Achievement of Financial Close

07-DEC-2017

Partial Commissioning 1

31-DEC-2018

RCOD

01-AUG-2019

Expected COD

01-AUG-2019

COD

17-AUG-2019