Private Power & Infrastructure Board |
||
|
Meridian Energy Limited |
||
|
Salient Features |
|
|
|
Project Company |
Meridian Energy Limited |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Scatec Sukhur BV |
|
|
Main Sponsor Shareholder |
75% |
|
|
Other Sponsors |
Nizam Energy (Pvt.) Limited Usman Ahmed Ali Ahmed |
|
|
Other Sponsors Shareholder |
25% Nizam Energy (Pvt.) Limited 24.99% Usman Ahmed 1.42 E-06% Ali Ahmed 1.42 E-06% |
|
|
Lenders |
i. Faysal Bank Limited ii. The Bank of Punjab iii. Pakistan Kuwait Investment Company (Private) Limited iv. Bank Islami Pakistan Limited. v. Nederlandse Financierings-Maatschappij voor Ontwikkelingslanden N.V. |
|
|
Province |
Sindh |
|
|
Location |
Goth Gagrwra, Saleh Pat, Sukkur |
|
|
Gross Capacity |
50MW |
|
|
Total Project Price (USD) |
30.342Million |
|
|
Debt Equity Ratio |
80:20 |
|
|
Levelized Tariff |
3.6683US c/kWh |
|
|
1-10 Years Tariff |
4.448US c/kWh |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
25Years |
|
|
EPC Contractor |
SCATEC Solar ASA |
|
|
Owner's Engineer |
SCATEC Solar ASA |
|
|
Annual Availability |
22.33% |
|
|
|
|
|
|
Important Events |
Issuance of LOI |
30-APR-2015 |
|
Tariff Determination |
21-FEB-2020 |
|
|
Date of issuance of LOS |
18-FEB-2021 |
|
|
Implementation Agreement |
18-FEB-2021 |
|
|
Direct Implementation Agreement |
19-FEB-2021 |
|
|
Power Purchase Agreement |
18-FEB-2021 EPA |
|
|
Direct Power Purchase Agreement |
18-FEB-2021 Direct EPA |
|
|
Achievement of Financial Close |
19-FEB-2021 |
|
|
COD |
19-JAN-2024 |
|