Private Power & Infrastructure Board |
||
|
Zorlu Enerji Pakistan Limited |
||
|
Salient Features |
|
|
|
Project Company |
Zorlu Enerji Pakistan Limited |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Zorlu Enerji Elektrik Uretium A.S. |
|
|
Main Sponsor Shareholder |
99.9999% |
|
|
Other Sponsors |
Olgun Zorlu, Selen Zorlu Melik, Mehmet Emre Zorlu. |
|
|
Other Sponsors Shareholder |
0.001% 0.01%, 0.01%, 0.01%, |
|
|
Lenders |
Lenders (Foreign): 1. Asian Development Bank 2. ECO Trade Development Bank 3. International Finance Corporation Intercreditor Agent: The Bank of New York Mellon Acting through its London Branch Offshore Security Trustee: BNY Melon Corporate Trustee Services Ltd. Offshore Account Bank: The Bank of New York Mellon acting through its London Branch Lenders (Local): Commercial Facility Financer: HBL Commercial Facility Arranger: HBL Commercial Facility Agent: HBL Onshore Security Trustee: HBL Onshore Account Bank: HBL |
|
|
Province |
Sindh |
|
|
Location |
JhImpir District Thattha , Sindh |
|
|
Gross Capacity |
56.4MW |
|
|
Net Capacity |
52.84MW |
|
|
Configuration |
5x1.2 MW (Vensys 62) & 28 x 1.8 MW (Vestas V90) WTG |
|
|
Total Project Price (USD) |
143.74Million |
|
|
Debt Equity Ratio |
70:30 |
|
|
Debt Amount USD |
100.618Million |
|
|
Equity Amount USD |
43.122Million |
|
|
Levelized Tariff |
13.3456US c/kWh US Cent 13.3456 /kWh Reference Exchange Rates 85.05 PKR/USD |
|
|
1-10 Years Tariff |
13.0681US c/kWh |
|
|
11-25 Years Tariff |
6.0207US c/kWh |
|
|
Power Purchaser |
National Transmission and Despatch Company (NTDC) |
|
|
Term of Project |
20Years |
|
|
EPC Contractor |
Zorlu Endustriyel Ve Enerji Tesisleri Insaat Ticaret A.S. |
|
|
Owner's Engineer |
Zorlu O&M Pakistan Private Limited |
|
|
Net Efficiency |
34.4% Net Capacity Factor 34.4% |
|
|
Annual Energy Yields |
159.010GWh Annual Benchmark Energy Generation 159.010 GWh |
|
|
Important Events |
|
|
|
Issuance of LOI |
12-MAR-2005 |
|
|
Tariff Determination |
19-JUL-2011 |
|
|
Date of issuance of LOS |
09-FEB-2009 |
|
|
Implementation Agreement |
12-JAN-2012 GOP Guarantee 25-MAY-2012 |
|
|
Direct Implementation Agreement |
11-APR-2012 |
|
|
Power Purchase Agreement |
12-JAN-2012 EPA |
|
|
Achievement of Financial Close |
29-MAR-2012 |
|
|
COD |
26-JUL-2013 |
|