Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

Hamza Sugar Mills Limited (HSML)

 Salient Features

 

 

Project Company

Hamza Sugar Mills Limited (HSML) PG Amount: US$ 14,250,000

Policy

(Framework for Power Cogeneration 2013) RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Mr. Muhammad Tayyab

Main Sponsor Shareholder

18.853%

Other Sponsors

Riaz Ahmed Muhammad Ahmed Muhammad Tariq Muhammad Tahir Khalid Riaz Zulfiqar Ahmed Naveed Riaz Kabeer Ahmed MST Amina Tayyab Mst Saba Tariq Mst Hina Tahir Mishal Tayyab Shifa Tayyab

Other Sponsors Shareholder

81.147% Riaz Ahmed 1.684% Muhammad Ahmed 12.500% Muhammad Tariq 12.873% Muhammad Tahir 12.873% Khalid Riaz 8.012% Zulfiqar Ahmed 7.033% Naveed Riaz 8.271% Kabeer Ahmed 5.136% MST Amina Tayyab 12.500% Mst Saba Tariq 0.127% Mst Hina Tahir 0.127% Mishal Tayyab 0.005% Shifa Tayyab 0.005%

Province

Punjab

Location

Jettha Bhutta, Khapur, Distric Rahim Yar Khan, Punjab

Gross Capacity

15MW

Technology

Steam Turbine Baggsse Conventional Steam Turbine based Power Plant

Configration

1 x 15.00MW Back Pressure Steam Turbine for Seasonal Operation + 1 x 15.00MW Extraction /Extraction Condensing Steam Turbine for off Season Operation) Steam Turbines: Guangzhau Skoda Jinma Ltd. China/Year 2012 Boiler: Sichuan Dongfang Boiler Industrial- Boiler Group Co. Ltd. China/Type: DHG 100-90/540- AG, Cap. 100T/Hr, 67 Bar (kg/cm2) Pressure 500°C/Year 2012

Total Project Price (USD)

14.949Million 14.949 million US Dollars (RS 1.465002 billion @exchange rate 98 Rs/USD)

Debt Equity Ratio

80:20

Debt Amount USD

11.9592Million

Equity Amount USD

2.9898Million

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

30Years

Primary Fuel

Imported Coal/Bagasse

Fuel Supplier

Hamza Sugar Mills Limited (HSML)

Annual Availability

45%

Annual Energy Yields

59,130GWh

 Important Events

 

 

Submission of Proposal

07-AUG-2013

Issuance of LOI

16-SEP-2013

Tariff Determination

12-SEP-2014

Submission of PG@US$ 5000/MW

13-OCT-2014

Date of issuance of LOS

11-DEC-2014

Implementation Agreement

11-DEC-2015

Power Purchase Agreement

11-AUG-2015

Achievement of Financial Close

27-APR-2016

COD

10-MAR-2017