Private Power & Infrastructure Board |
||
|
Lakeside Energy (Pvt.) Limited |
||
|
Salient Features |
|
|
|
Project Company |
Lakeside Energy (Pvt.) Limited |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Naveena Exports Limited |
|
|
Main Sponsor Shareholder |
75% |
|
|
Other Sponsors |
Fawad Anwar |
|
|
Other Sponsors Shareholder |
25% |
|
|
Lenders |
Lenders (Foreign): 1. Nederlandse Financierings-Maatschappij Voor Ontwikkelingslanden N.V Anna Van Saksenlaan 71, 2509 AB, The Hague, Netherland 2. DEG-Deutsche Investitions-und Entwicklungsgesellschaft mbH, Germany (DEG) by accession pursuant to the CTA Deed of Accession Lenders (Local) Lenders: FBL & Bank of Punjab Intercreditor Agent: FBL LCY Facility Agent: FBL Investment Agent FBL Offshore Account Bank: United National Bank Ltd. Onshore Account Bank: FBL Offshore Security Agent: UBL Onshore Security Agent: FBL |
|
|
Province |
Sindh |
|
|
Location |
Jhimpir Sindh |
|
|
Gross Capacity |
50MW |
|
|
Net Capacity |
47.9MW |
|
|
Configuration |
25 x 2.0 MW (Gamesa G-114) WTG |
|
|
Total Project Price (USD) |
63.906Million |
|
|
Debt Equity Ratio |
80:20 |
|
|
Debt Amount USD |
51.1248Million |
|
|
Equity Amount USD |
12.7812Million Reference Exchange Rates 120 PKR/USD |
|
|
Levelized Tariff |
4.7154US c/kWh |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
25Years |
|
|
EPC Contractor |
Power China huadong |
|
|
Owner's Engineer |
HYDROCHINA INTERNATIONAL ENGINEERING COMPANY LTD - WARRANTY PERIOD O&M OPERATOR, SIEMENS GAMESA RENEWABLE ENERGY PRIVATE LIMITED - 11 YEARS O&M OPERATOR |
|
|
Net Efficiency |
38% Net Capacity Factor 38% |
|
|
Important Events |
|
|
|
Issuance of LOI |
24-JUL-2015 |
|
|
Tariff Determination |
19-NOV-2018 |
|
|
Date of issuance of LOS |
08-NOV-2019 |
|
|
Implementation Agreement |
12-NOV-2019 GOP Guarantee 18-Nov-2019 |
|
|
Direct Implementation Agreement |
15-NOV-2019 |
|
|
Power Purchase Agreement |
11-NOV-2019 |
|
|
Direct Power Purchase Agreement |
14-NOV-2019 |
|
|
Achievement of Financial Close |
08-NOV-2019 |
|
|
COD |
14-APR-2022 |
|