Appolo Solar Development Pakistan Limited

 Salient Features

 

Project Company

Appolo Solar Development Pakistan Limited

Policy

RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Appolo Solar Development Limited

Main Sponsor Shareholder

99.97%

Other Sponsors

Jun Guo, Yuan Li, Jian Jia.

Other Sponsors Shareholder

0.03% Jun Guo 0.01%, Yuan Li 0.01%, Jian Jia 0.01%

Lenders

i. China Development Bank Corporation ii. Export-Import Bank of China iii. Industrial and Commercial Bank of China Corporation

Province

Punjab

Location

QASP, Bahawalpur

Net Capacity

100MW

Total Project Price (USD)

151.4314Million

Debt Equity Ratio

75:25

Levelized Tariff

13.0288US c/kWh

11-25 Years Tariff

6.4840US c/kWh Exchange Rate 104.9 PKR / USD

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

25Years

EPC Contractor

China First Metallurgical Group Company Limited

Owner's Engineer

Zonergy

Net Efficiency

17.99%%

 Important Events

 

 

Issuance of LOI

27-MAY-2015

Tariff Determination

26-MAY-2015 Tariff Determination 26-May-2015 (Original) 26-Oct-2015 (Revised) 16-Nov-2017 (COD Adjustment)

Date of issuance of LOS

16-JUN-2015 TLOS

Implementation Agreement

25-JUN-2015 GOP Guarantee 06-NOV-2015 Supplemental Agreement 22-JAN-2018

Direct Implementation Agreement

29-OCT-2015

Power Purchase Agreement

26-JUN-2015 EPA

Direct Power Purchase Agreement

03-NOV-2015 Direct EPA

Achievement of Financial Close

06-NOV-2015

COD

31-MAY-2016