Private Power & Infrastructure
Board |
||
|
1180 MW RLNG Bhikki Power Project |
||
|
Salient Features |
|
|
|
Project Company |
Quaid-e-Azam Thermal Power (Pvt.) Ltd. |
|
|
Policy |
Power Policy 2015 |
|
|
Category |
Commissioned |
|
|
Main Sponsor |
Government of Punjab |
|
|
Main Sponsor Shareholder |
100% |
|
|
Province |
Punjab |
|
|
Location |
Bhikki, district Sheikhupura, Punjab |
|
|
Gross Capacity |
1180.13MW (at RSC) |
|
|
Net Capacity |
1156.67MW (at RSC) |
|
|
Transmission Voltage Level |
500kV |
|
|
Technology |
Combined Cycle Gas Turbine (GE H Class - 9HA.01 CCGT) (Multi-Shaft) |
|
|
Configuration |
2GT+2HRSG+1ST |
|
|
Total Project Price (USD) |
722.6Million |
|
|
Debt Equity Ratio |
75 : 25 |
|
|
Levelized Tariff |
8.064US c/kWh |
|
|
Power Purchaser |
CPPA-G |
|
|
Term of Project |
30Years |
|
|
Primary Fuel |
R-LNG |
|
|
Secondary Fuel |
HSD |
|
|
Fuel Supplier |
SNGPL |
|
|
EPC Contractor |
JV of Harbin Electric International (HEI) and Habib Rafiq Ltd. |
|
|
Net Efficiency |
61.59% |
|
|
Annual Availability |
92% |
|
|
Important Events |
|
|
|
Submission of Proposal |
24-JUN-2015 |
|
|
Issuance of Notice to Proceed |
06-JUL-2015 |
|
|
Issuance of LOI |
13-JUL-2015 |
|
|
Generation License Application |
15-JUL-2016 |
|
|
Tariff Determination |
14-APR-2016 |
|
|
Date of issuance of LOS |
09-MAY-2016 |
|
|
Implementation Agreement |
16-AUG-2016 |
|
|
Power Purchase Agreement |
22-JUL-2016 |
|
|
Fuel Supply Agreement |
22-JUL-2016 |
|
|
Achievement of Financial Close |
22-AUG-2016 |
|
|
Partial Commissioning 1 |
17-JUN-2017 GT-1 Commissioning |
|
|
Partial Commissioning 2 |
08-MAY-2017 GT-2 Commissioning |
|
|
COD |
20-May-2018 |
|