Indus Wind Energy Limited

 Salient Features

 

 

Project Company

Indus Wind Energy Limited

Policy

RE Policy 2006

Category

Commissioned

Sub Category

Other

Main Sponsor

Indus Dyeing & Manufacturing Co. Ltd (226,031,193 shares)

Main Sponsor Shareholder

100%

Other Sponsors

Nominee shares to Directors (8 shares, 1 each)

Other Sponsors Shareholder

0%

Lenders

Lenders (Local): PKR Financers: HBL, Askari Bank Limted, Soneri Bank Limietd Onshore Account Bank: HBL Offshore Account Bank: HBL UK Rupee Facility Agent: HBL Facility Agent: HBL Onshore Security Trustee: HBL Offshore Security Trustee: HBL UK

Province

Sindh

Location

Jhimpir, Sindh

Gross Capacity

50MW

Net Capacity

47.9MW

Configuration

25 x 2.0 MW (GE 116-2.0) WTG

Total Project Price (USD)

64.072Million

Debt Equity Ratio

80:20

Debt Amount USD

51.2575Million

Equity Amount USD

12.8144Million

Levelized Tariff

4.7931US c/kWh Reference Exchange Rates: 120 PKR/USD

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

25Years

EPC Contractor

Power China huadong

Owner's Engineer

Hydrochina International Engineer Company Limited Pakistan (WP O&M 2 years), General Electric International Inc. (LT O&M 11 Years)

Net Efficiency

38% Net Capacity Factor 38%

 Important Events

 

 

Issuance of LOI

28-AUG-2015

Tariff Determination

19-NOV-2018

Date of issuance of LOS

08-NOV-2019

Implementation Agreement

12-NOV-2019 GOP Guarantee 18-Nov-2019

Direct Implementation Agreement

15-NOV-2019

Power Purchase Agreement

11-NOV-2019 EPA

Direct Power Purchase Agreement

14-NOV-2019 Direct EPA