Private Power & Infrastructure Board |
||
|
Tricon Boston Consulting Corporation (Pvt.) Limited - A |
||
|
Salient Features |
|
|
|
Project Company |
Tricon Boston Consulting Corporation (Pvt.) Limited - A |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
Sapphire Textile Mills Limited |
|
|
Main Sponsor Shareholder |
57.125% |
|
|
Other Sponsors |
Renew Power, Bank Alfalah Limited, Sapphire Finishing Mills Limited, Diamond Fabrics Limited, sapphire Fibres Limited. |
|
|
Other Sponsors Shareholder |
42.875% 12.25%, 9.25%, 7.125%, 7.125%, 7.125%, |
|
|
Lenders |
Lenders (Foreign): International Finance Corporation (IFC) Asian Development Bank (ADB) Islamic Development Bank (IDB) Deutsche Investitions- und Entwicklungsgesellschaft (DEG) (German Investment Corporation) Intercreditor Agent: Citi Bank Europe Onshore Security Trustee: Citi Bank N.A. Offshore Security Trustee: Citi Bank London Branch Onshore Account Bank: Citi Bank N.A. Offshore Account Bank: Citi Bank N.A. London Branch |
|
|
Province |
Sindh |
|
|
Location |
Jhimpir, Thatta, Sindh |
|
|
Gross Capacity |
49.735MW |
|
|
Net Capacity |
47.891MW |
|
|
Configuration |
29 x 1.715 MW (GE 1.7-103.5) WTG |
|
|
Total Project Price (USD) |
106.47Million |
|
|
Debt Equity Ratio |
75:25 |
|
|
Debt Amount USD |
79.8525Million |
|
|
Equity Amount USD |
26.6175Million |
|
|
Levelized Tariff |
10.4481US c/kWh US Cent 10.4481 (at COD 10.5484) Reference Exchange Rates 101.5 PKR/USD |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
20Years |
|
|
EPC Contractor |
Hydrochina International Engineering Company Limited |
|
|
Owner's Engineer |
General Electric (GE) |
|
|
Net Efficiency |
35% Net Capacity Factor 35% |
|
|
Important Events |
|
|
|
Issuance of LOI |
18-FEB-2013 |
|
|
Tariff Determination |
13-MAY-2016 |
|
|
Date of issuance of LOS |
08-NOV-2016 |
|
|
Implementaion Agreement |
14-APR-2017 GOP Guarantee 10-MAY-2017 |
|
|
Direct Implementation Agreement |
25-APR-2017 |
|
|
Power Purchase Agreement |
13-APR-2017 EPA |
|
|
Direct Power Purchase Agreement |
05-MAY-2017 Direct EPA |
|
|
Achievement of Financial Close |
10-MAY-2017 |
|
|
COD |
16-AUG-2018 |
|