Salient Features |
|
|
|
Project Company |
Three Gorges Third Wind Farm Pakistan (Pvt.) Limited |
|
|
Policy |
RE Policy 2006 |
|
|
Category |
Commissioned |
|
|
Sub Category |
Other |
|
|
Main Sponsor |
China Three Gorges South Asia Investment Limited |
|
|
Main Sponsor Shareholder |
100% |
|
|
Lenders |
Lenders (Foreign): China Development Bank |
|
|
Province |
Sindh |
|
|
Location |
Jhimpir, Thatta, Sindh |
|
|
Gross Capacity |
49.5MW |
|
|
Net Capacity |
48.34MW |
|
|
Configuration |
33 x 1.5 MW (GoldWind- GW 82) WTG |
|
|
Total Project Price (USD) |
106.25Million |
|
|
Debt Equity Ratio |
75:25 |
|
|
Debt Amount USD |
79.6875Million |
|
|
Equity Amount USD |
26.5625Million |
|
|
Levelized Tariff |
10.4481US c/kWh Reference Exchange Rate 101.5 PKR/USD |
|
|
Power Purchaser |
Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL) |
|
|
Term of Project |
20Years |
|
|
EPC Contractor |
shanghai Investigation Design and Research Institute Co. Ltd |
|
|
Owner's Engineer |
China Three Gorges Power Operations International Co., Ltd. (CTGO) |
|
|
Net Efficiency |
35% Net Capacity Factor |
|
|
Important Events |
|
|
|
Issuance of LOI |
05-OCT-2006 |
|
|
Tariff Determination |
01-APR-2016 |
|
|
Date of issuance of LOS |
01-AUG-2016 |
|
|
Implementation Agreement |
23-DEC-2016 (GOP) Guarantee 17-MAR-2017 |
|
|
Direct Implementation Agreement |
16-MAR-2017 |
|
|
Power Purchase Agreement |
15-DEC-2016 EPA |
|
|
Direct Power Purchase Agreement |
08-MAR-2017 Direct EPA |
|
|
Achievement of Financial Close |
17-MAR-2017 |
|
|
COD |
09-JUL-2018 |
|