Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

1230MW(Gross) RLNG based Combine Cycle Power Plant at Haveli Bahadur Shah, Dist Jhang Punjab

 Salient Features

 

 

Project Company

National Power Parks Management Company (Pvt) Ltd (NPPMCL), MoW&P

Policy

Power Policy 2015

Category

Commissioned

Main Sponsor

Mo Energy (Power Division), GoP

Main Sponsor Shareholder

100%

Province

Punjab

Location

Haveli Bahadur Shah, district Jhang, Punjab

Gross Capacity

1230.54MW

Net Capacity

1215MW

Technology

Combined Cycle Gas Turbine (GE H Class - 9HA.01 CCGT) (Multi-shaft)

Configuration

2GT-2HRSG+1ST

Total Project Price (USD)

784Million

Debt Equity Ratio

70 : 30

Levelized Tariff

8.76US c/kWh

Power Purchaser

CPPA-G

Term of Project

30Years

Primary Fuel

R-LNG

Secondary Fuel

HSD

Fuel Supplier

SNGPL

EPC Contractor

Power Construction Corporation of China . Civil: HUBEI . Mechanical: TAIAN JIAN . Electrical: HBYN . other: LAI WU SHAO, JIANG XI

Net Efficiency

62.2%

Annual Availability

92%

 Important Events

 

 

Submission of Proposal

25-FEB-2016

Issuance of Notice to Proceed

15-MAR-2016

Issuance of LOI

12-APR-2016

Generation License Application

21-APR-2016

Tariff Determination

09-AUG-2016

Date of issuance of LOS

22-SEP-2016

Implementation Agreement

14-NOV-2016

Power Purchase Agreement

29-OCT-2016

Fuel Supply Agreement

29-OCT-2016

Achievement of Financial Close

28-NOV-2016

Partial Commissioning 1

18-JUL-2017

Partial Commissioning 2

18-JUL-2017

COD

09-May-2018