1230MW(Gross) RLNG based Combine Cycle Power Plant at Haveli Bahadur Shah, Dist Jhang Punjab |
||
|
Salient Features |
|
|
|
Project Company |
National Power Parks Management Company (Pvt) Ltd (NPPMCL), MoW&P |
|
|
Policy |
Power Policy 2015 |
|
|
Category |
Commissioned |
|
|
Main Sponsor |
Mo Energy (Power Division), GoP |
|
|
Main Sponsor Shareholder |
100% |
|
|
Province |
Punjab |
|
|
Location |
Haveli Bahadur Shah, district Jhang, Punjab |
|
|
Gross Capacity |
1230.54MW |
|
|
Net Capacity |
1215MW |
|
|
Technology |
Combined Cycle Gas Turbine (GE H Class - 9HA.01 CCGT) (Multi-shaft) |
|
|
Configuration |
2GT-2HRSG+1ST |
|
|
Total Project Price (USD) |
784Million |
|
|
Debt Equity Ratio |
70 : 30 |
|
|
Levelized Tariff |
8.76US c/kWh |
|
|
Power Purchaser |
CPPA-G |
|
|
Term of Project |
30Years |
|
|
Primary Fuel |
R-LNG |
|
|
Secondary Fuel |
HSD |
|
|
Fuel Supplier |
SNGPL |
|
|
EPC Contractor |
Power Construction Corporation of China . Civil: HUBEI . Mechanical: TAIAN JIAN . Electrical: HBYN . other: LAI WU SHAO, JIANG XI |
|
|
Net Efficiency |
62.2% |
|
|
Annual Availability |
92% |
|
|
Important Events |
|
|
|
Submission of Proposal |
25-FEB-2016 |
|
|
Issuance of Notice to Proceed |
15-MAR-2016 |
|
|
Issuance of LOI |
12-APR-2016 |
|
|
Generation License Application |
21-APR-2016 |
|
|
Tariff Determination |
09-AUG-2016 |
|
|
Date of issuance of LOS |
22-SEP-2016 |
|
|
Implementation Agreement |
14-NOV-2016 |
|
|
Power Purchase Agreement |
29-OCT-2016 |
|
|
Fuel Supply Agreement |
29-OCT-2016 |
|
|
Achievement of Financial Close |
28-NOV-2016 |
|
|
Partial Commissioning 1 |
18-JUL-2017 |
|
|
Partial Commissioning 2 |
18-JUL-2017 |
|
|
COD |
09-May-2018 |
|