PATRIND HYDROPOWER PROJECT |
Salient Features |
| Company |
Star Hydropower Limited |
| Capacity |
147 MW (Gross) |
| Location |
Muzaffarabad AJK |
| Fuel |
Hydro |
| Technology |
Hydro |
| Configuration |
50 MW x 3 Francis Turbines. |
| Power Purchaser |
CPPAG (NTDCL) |
| Term of Project |
30 Years |
| Registered Address |
Usman Square 3rd & 4th Floor, Main Double Road E-11/2, Islamabad |
| Email |
[email protected] |
Important Milestones |
| Issuance of Letter of Interest (LOI) |
26th October 2005 |
| Issuance of Letter of Support (LOS) |
30th June 2010 |
| Date of Financial Closing |
20th December 2012 |
| Commissioning Date |
8th November 2017 |
Contractual Agreements |
| Implementation Agreement (IA) |
February 11, 2012 |
| Power Purchase Agreement (PPA) |
March 8, 2012 |
| WUA (AJK) |
Feb. 11, 2012 |
| WUA (KPK) |
Oct. 31, 2011 |