1223MW(Gross) RLNG based Combine Cycle Power Plant at Balloki, Dist Kasur Punjab |
||
|
Salient Features |
|
|
|
Project Company |
National Power Parks Management Company (Pvt.) Ltd. (NPPMCL), Mo Energy |
|
|
Policy |
Power Policy 2015 |
|
|
Category |
Commissioned |
|
|
Main Sponsor |
Mo Energy (Power Division) GoP |
|
|
Main Sponsor Shareholder |
100% |
|
|
Province |
Punjab |
|
|
Location |
Balloki, district Kasur, Punjab |
|
|
Gross Capacity |
1223.1MW |
|
|
Net Capacity |
1205MW |
|
|
Transmission Voltage Level |
500kV |
|
|
Technology |
Combined Cycle Gas Turbine |
|
|
Configuration |
2GT + 2HRSG + 1 ST |
|
|
Total Project Price(USD) |
763.2Million |
|
|
Debt Equity Ratio |
70 :30 |
|
|
Levelized Tariff |
10.018US c/kWh |
|
|
Power Purchaser |
CPPA-G |
|
|
Term of Project |
30Years |
|
|
Primary Fuel |
RLNG 7 USD/MMBTU (HHV) |
|
|
Secondary Fuel |
HSD HSD Price Rs.42.91/Liter |
|
|
Fuel Supplier |
SNGPL |
|
|
EPC Contractor |
Harbin Electric International (HEI) Civil: Habib Rafiq Ltd. Mechanical: TEPC, China Electrical: TEPC, China |
|
|
Net Efficiency |
61.63% |
|
|
Annual Availability |
92% |
|
|
Important Events |
|
|
|
Submission of Proposal |
25-Feb-2016 |
|
|
Issuance of Notice to Proceed |
15-Mar-2016 |
|
|
Issuance of LOI |
12-Apr-2016 |
|
|
Generation License Application |
21-Apr-2016 |
|
|
Tariff Determination |
9-Aug-2016 |
|
|
Date of issuance of LOS |
22-Sep-2016 |
|
|
Implementation Agreement |
14-NOV-2016 |
|
|
Power Purchase Agreement |
29-OCT-2016 |
|
|
Fuel Supply Agreement |
29-OCT-2016 |
|
|
Achievement of Financial Close |
28-NOV-2016 |
|
|
Partial Commissioning 1 |
13-Aug-2017 |
|
|
Partial Commissioning 2 |
30-AUG-2017 |
|
|
COD |
29-JUL-2018 |
|