1223MW(Gross) RLNG based Combine Cycle Power Plant at Balloki, Dist Kasur Punjab

 Salient Features

 

 

Project Company

National Power Parks Management Company (Pvt.) Ltd. (NPPMCL), Mo Energy

Policy

Power Policy 2015

Category

Commissioned

Main Sponsor

Mo Energy (Power Division) GoP

Main Sponsor Shareholder

100%

Province

Punjab

Location

Balloki, district Kasur, Punjab

Gross Capacity

1223.1MW

Net Capacity

1205MW

Transmission Voltage Level

500kV

Technology

Combined Cycle Gas Turbine

Configuration

2GT + 2HRSG + 1 ST

Total Project Price(USD)

763.2Million

Debt Equity Ratio

70 :30

Levelized Tariff

10.018US c/kWh

Power Purchaser

CPPA-G

Term of Project

30Years

Primary Fuel

RLNG 7 USD/MMBTU (HHV)

Secondary Fuel

HSD HSD Price Rs.42.91/Liter

Fuel Supplier

SNGPL

EPC Contractor

Harbin Electric International (HEI) Civil: Habib Rafiq Ltd. Mechanical: TEPC, China Electrical: TEPC, China

Net Efficiency

61.63%

Annual Availability

92%

 Important Events

 

 

Submission of Proposal

25-Feb-2016

Issuance of Notice to Proceed

15-Mar-2016

Issuance of LOI

12-Apr-2016

Generation License Application

21-Apr-2016

Tariff Determination

9-Aug-2016

Date of issuance of LOS

22-Sep-2016

Implementation Agreement

14-NOV-2016

Power Purchase Agreement

29-OCT-2016

Fuel Supply Agreement

29-OCT-2016

Achievement of Financial Close

28-NOV-2016

Partial Commissioning 1

13-Aug-2017

Partial Commissioning 2

30-AUG-2017

COD

29-JUL-2018