Private Power & Infrastructure Board
Ministry of Energy (Power Division)
Government of Pakistan

2x660MW Imported Coal Based IPP-Power China(Sinohydro Resouces/Al Mirqab Capital Qatar)

 Salient Features

 

 

Project Company

Port Qasim Electric Power Company (Private) Limited

Sub Category

CPEC

Main Sponsor

Sinohydro Resources Ltd.China

Main Sponsor Shareholder

51%

Other Sponsors

Al Mirqab Capital, Qatar

Other Sponsors Shareholder

49%

Lenders

Export and Import Bank of China (CEXIM)

Province

Sindh

Location

Port Qasim, Karachi

Gross Capacity

1320MW

Net Capacity

1214MW

Configuration

2 x 660 MW

Total Project Price (USD)

1912.2Million

Debt Equity Ratio

75:25

Levelized Tariff

8.3601US c/kWh

Levelized CPP

3.5039US c/kWh

Levelized EPP

4.8561US c/kWh

1-10 Years Tariff

9.0642US c/kWh

11-30 Years Tariff

7.0419US c/kWh

Power Purchaser

Central Power Purchasing Agency (Guarantee) Limited (CPPA-GL)

Term of Project

30Years

Primary Fuel

Imported Coal

 Important Events

 

 

Issuance of LOI

21-MAY-2014

Generation License Application

03-FEB-2015

Tariff Determination

13-FEB-2015

Date of issuance of LOS

17-APR-2015

Implementation Agreement

18-APR-2015

Power Purchase Agreement

18-APR-2015

Achievement of Financial Close

22-DEC-2015

Partial Commissioning 1

10-NOV-2017

Partial Commissioning 2

15-JAN-2018

COD

25-April-2018