Current Portfolio of Upcoming Power Generation Projects
As on February 20, 2024
Sr.
# |
Project | Sponsor/
Company Name |
Location | Fuel | Capacity (MW) |
Expected COD/Remarks | ||
2024 | ||||||||
1 | Shah Taj Sugar Mills Project | Shah Taj Sugar Mills | Mandi Baha-ud-Din, Punjab | Bagasse | 32 | Jun-24
(Under Construction) |
||
2 | Zorlu Solar Pakistan Ltd | Zorlu Enerji, Turkiye | QASP, Bahawalpur, Punjab | Solar | 100 | Oct- 24
TLOS issued. FC in progress |
||
3* | Suki Kinari Hydropower Project | S.K Hydro Pvt Ltd | Kunhar River, Mansehra, KP | Hydel | 884 | Nov-24
(Under Construction) |
||
Sub Total (2024) | 1,016 | |||||||
2025 | ||||||||
4 | Access Solar (Pvt) Ltd | Tech Access FZLL | Pind Dadan Khan, Jhelum, Punjab | Solar | 11.52 | Mar-25
LOS issued. FC in progress |
||
5 | Access Electric (Pvt) Ltd | Tech Access FZLL | Pind Dadan Khan, Jhelum, Punjab | Solar | 10 | Mar-25
LOS issued. FC in progress |
||
6 | Safe Solar Pakistan (Pvt) Ltd | Safe Solar | Bahawalnagar, Punjab | Solar | 10.27 | Aug-25
LOS issued. FC in progress |
||
7 | Siachen Energy Ltd | Muhammad Sohail Shamsi | Ghulamullah Road, Taluka Mirpur Sakro, Dist.Thatta, Sindh | Solar | 100 | Dec-25
Generation License Acquired. Tariff determination is awaited from NEPRA |
||
8 | Riali-II Hydropower Project | Riali Hydro Power Co. | Ghori Wala Nullah, Muzaffarabad AJ&K | Hydel | 7.08 | Dec-25**
LOS issued Under FC / under Construction |
||
9* | 300 MW coal based Power Project | CIHC Pak Power Co. Ltd | Gwadar, Balochistan | Imported Coal | 300 | Dec-25**
LOS issued FC in progress |
||
Sub Total (2025) | 438.87 | |||||||
2026 | ||||||||
10* | Western Energy (Private) Limited | Tapal Family | Jhimpir, District Thatta, Sindh | Wind | 50 | Feb-26
Tariff determination is awaited from NEPRA |
||
11 | Transatlantic Energy Private Limited | Waqas A Qureshi, Pervaiz Qureshi, Ali Muskatiya, Shahreyar Nawabi, Burkat A Qureshi | Jhimpir, District Thatta, Sindh | Wind | 50 | Feb-26
Tariff determination is awaited from NEPRA |
||
12 | Kathai-II Hydropower Project | Kathai-II Hydro (Pvt) Ltd. | Kathai Nullah, Hattian, AJ&K | Hydel | 8.00 | Dec-26
LOS issued FC in Progress |
||
Sub Total (2026) | 108.00 | |||||||
2028 | ||||||||
13 | Oracle Power Project | Oracle Coal Fields PLC England | Thar Block VI, Sindh | Thar Coal | 1,320 | Dec-28
Project Proposal is Under Review. Further processing will be as per IGCEP |
||
Sub Total (2028) | 1,320 | |||||||
2029 | ||||||||
14 | Turtonas-Uzghor Hydropower Project
(candidate project in the IGCEP portfolio) |
Sinohydro-Sachal Consortium | Golen Gol River, Chitral Valley KP | Hydel | 82.25 | Dec-29
LOI issued. FS completed and approved by POE. Further processing will be as per IGCEP |
||
Sub Total (2029) | 82.25 | |||||||
2030 | ||||||||
15* | Azad Pattan Hydropower Project (committed project in IGCEP portfolio) | Azad Pattan Power (Pvt) Ltd. | Jehlum River, Sudhnoti, AJ&K | Hydel | 700.7 | Sep-30
LOS issued FC in progress |
||
Sub Total (2030) | 700.7 | |||||||
2031 | ||||||||
16* | Kohala Hydropower Project
(committed project in IGCEP portfolio) |
Kohala Hydro Company Limited | Jehlum River/ Kohala, AJ&K | Hydel | 1,124 | Mar-31
LOS issued FC in progress |
||
17 | Ashkot Hydropower Project
(candidate project in the IGCEP portfolio) |
Ashkot Energy (Pvt) Ltd. | Neelum River, AJ&K | Hydel | 300 | Sep-31
Project has been transferred by GoAJK to PPIB for further processing as per IGCEP |
||
18 | Rajdhani Hydropower Project
(candidate / optimized project in IGCEP portfolio) |
– | Poonch River AJ&K | Hydel | 132 | Dec-31
To be processed as per the requirements of new capacity in the IGCEP |
||
Sub Total (2031) | 1,556 | |||||||
2032 | ||||||||
19 | Mahl Hydropower Project
(optimized project in IGCEP portfolio) |
CWE Investment Corporation/ China Three Gorges & Trans Tech Pakistan | Jehlum River, AJ&K/ Punjab | Hydel | 640 | Dec-32
LOI issued. FS completed and approved by POE. Tariff determined by NEPRA. Further processing will be as per IGCEP |
||
Sub Total (2032) | 640 | |||||||
Other Projects | ||||||||
20 | Athmuqam Hydropower Project
(candidate project in the IGCEP portfolio) |
Korea Hydro and Nuclear Company | Neelum River, AJ&K | Hydel | 450 | LOI issued.
FS completed and approved by POE. Further processing will be as per IGCEP |
||
21 | Kaigah Hydropower Project | – | Kaigah, Indus River, KP | Hydel | 548 | To be processed as per the requirements of new capacity in the IGCEP | ||
22 | Chakothi-Hattian Hydropower Project | – | Muzaffarabad, AJ&K | Hydel | 500 | |||
23 | Neckeherdim-Paur Hydropower Project | – | Yarkun River, Chitral Valley KP | Hydel | 80 | |||
24 | Hatim Power Project | Pakistan Petroleum Ltd. | Near Shahdadpur, District Sangarh, Sindh | Low BTU Gas | 20 | |||
Sub Total (2033) | 1,598 | |||||||
Grand Total | 7,459.82 |
* CPEC Projects
** Likely to get late due to various issues
COD = Commercial Operation Date, FC = Financial Close, LOS = Letter of Support, LOI = Letter of Intent/Interest, FS = Feasibility Study, POE = Panel of Experts, IGCEP = Indicative Generation Capacity Expansion Plan