TAPAL ENERGY POWER PROJECT |
Salient Features |
Company |
Tapal Energy (Pvt.) Limited |
Capacity |
126 MW (Gross) |
Location |
District West, Karachi |
Fuel |
Furnace Oil |
Technology |
Diesel Engines |
Plant Configuration |
12 Oil Fired Engines |
Power Purchaser |
KESC |
Fuel Supplier |
PSO |
Term of the PPA |
22 Years |
Registered Address |
Tapal Energy Limited F-25, Block 5, Kehkashan, Clifton Karachi. |
Email |
telcoff@tapalenergy.com.pk |
Important Milestones |
Submission of Application |
June 16, 1994 |
Issuance of Letter of Interest (LOI) |
June 28, 1994 |
Issuance of Letter of Support (LOS) |
September 18, 1994 |
Date of Financial Closing |
March 11, 1996 |
Commissioning Date |
June 20, 1997 |
Net / Dependable Capacity |
120 MW |
Contractual Agreements |
Implementation Agreement (IA) |
August 8, 1994 |
Power Purchase Agreement (PPA) |
September 26, 1995 |
Fuel Supply Agreement (FSA) |
March 7, 1996 |
GOP Guarantee |
April 18, 1996 |