ROUSCH POWER PROJECT |
Salient Features |
Company |
Rousch (Pakistan) Power Limited |
Capacity |
450 MW (Gross) |
Location |
Abdul Hakeem (Near Sidhnai Barrage), District Khanewal (about 85 KM North-East of Multan) |
Fuel |
Residual Fuel Oil (RFO) |
Technology |
Combined Cycle |
Plant Configuration |
Two Gas Turbines + One Steam Turbine |
Power Purchaser |
WAPDA |
Fuel Supplier |
PSO |
Term of the PPA |
30 Years |
Registered Address |
Rousch (Pakistan) Power Ltd. 39-C/IV, Block-6, P.E.C.H.S. Karachi. |
Email |
rousch@rouschpak.com |
Important Milestones |
Submission of Application |
May 10, 1994 |
Issuance of Letter of Interest (LOI) |
June 22, 1994 |
Issuance of Letter of Support (LOS) |
August 8, 1994 |
Date of Financial Closing |
April 7, 1996 |
Commissioning Date |
December 11, 1999 |
Net / Dependable Capacity |
395 MW |
Contractual Agreements |
Implementation Agreement (IA) |
June 15, 1995 |
Amended and Restated |
March 31, 1996 |
Power Purchase Agreement (PPA) |
February 25, 1996 |
Amendment No. 1 |
May 25, 1996 |
Amendment No. 2 |
July 7, 1996 |
Fuel Supply Agreement (FSA) |
July 23, 1995 |
GOP Guarantee |
August 2, 1996 |