SOUTHERN ELECTRIC POWER PROJECT |
Salient Features |
Company |
Southern Electric Power Project |
Capacity |
117 MW (Gross) |
Location |
Raiwind, Lahore |
Fuel |
Residual Fuel Oil (RFO) |
Technology |
Diesel Engines |
Plant Configuration |
5 Units |
Power Purchaser |
WAPDA |
Fuel Supplier |
PSO |
Term of the PPA |
30 Years |
Registered Address |
Southern Electric Power Co. Ltd. 90-West, 6th Floor Razia Sharif Plaza, Blue Area Islamabad. |
Email |
info@sepcol.com |
Important Milestones |
Submission of Application |
June 12, 1994 |
Issuance of Letter of Interest (LOI) |
June 28, 1994 |
Issuance of Letter of Support (LOS) |
August 3, 1994 |
Date of Financial Closing |
October 25, 1995 |
Commissioning Date |
July 12, 1999 |
Net / Dependable Capacity |
119 MW |
Contractual Agreements |
Implementation Agreement (IA) |
November 23, 1994 |
Supplement No. 1 |
March 7, 1994 |
Power Purchase Agreement (PPA) |
November 17, 1994 |
Amendment No. 1 |
October 25, 1995 |
Fuel Supply Agreement (FSA) |
November 30, 1994 |
Amendment No. 1 |
October 24,1995 |
GOP Guarantee |
August 26, 1996 |
Cost Overruns |
Yes |