PATRIND HYDROPOWER PROJECT |
Salient Features |
Company |
Star Hydropower Limited |
Capacity |
147 MW (Gross) |
Location |
Muzaffarabad AJK |
Fuel |
Hydro |
Technology |
Hydro |
Configuration |
50 MW x 3 Francis Turbines. |
Power Purchaser |
CPPAG (NTDCL) |
Term of Project |
30 Years |
Registered Address |
Usman Square 3rd & 4th Floor, Main Double Road E-11/2, Islamabad |
Email |
patrind@patrind.com |
Important Milestones |
Issuance of Letter of Interest (LOI) |
26th October 2005 |
Issuance of Letter of Support (LOS) |
30th June 2010 |
Date of Financial Closing |
20th December 2012 |
Commissioning Date |
8th November 2017 |
Contractual Agreements |
Implementation Agreement (IA) |
February 11, 2012 |
Power Purchase Agreement (PPA) |
March 8, 2012 |
WUA (AJK) |
Feb. 11, 2012 |
WUA (KPK) |
Oct. 31, 2011 |