Important Milestones
|
|
Submission of Proposal
|
06-06-2003
|
|
Issuance of Letter
of Interest
(LOI)
|
12-02-2004
|
|
Issuance of Letter of
Support (LOS)
|
01-11-2005
|
|
Date of Financial
Closing
|
16-12-2006
|
|
Commissioning Date
|
24-05-2010
|
|
Net / Dependable Capacity
|
213 MW
|
|
Contractual Agreements
|
|
Implementation Agreement (IA)
|
10-11-2006
|
|
Power
Purchase Agreement (PPA)
|
08-11-2006
|
|
Gas Supply
Agreement (GSA)
|
18-10-2006
|