NEW BONG ESCAPE HYDROPOWER PROJECT |
Salient Features |
Company |
Laraib Energy Limited |
Capacity |
84 MW (Gross) |
Location |
7Km Downstream Mangla Dam, AJK |
River |
Jhelum |
Project Type |
Run of River |
Energy |
470 Gwh |
Term of the PPA |
25 Years |
Registered Address |
12-B/1, G-8 Markaz, Islamabad |
Email |
mail@laraibenergy.com |
Important Milestones |
Issuance of Letter of Support (LOS) by GOAJK |
18th May 1996, valid until 2nd Dec. 2009 |
Signing of Amended & Restated GOPIA |
31st August 2007 |
Signing of EPC contract |
19th June 2009 |
Signing of Amended & Restated PPA |
22nd October 2009 |
Signing of Amended & Restated AJKIA |
27th October 2009 |
Signing of AJKIA-DA, WUA-DA, GOPIA-DA |
10th November 2009 |
Signing of PPA-DA |
20th November 2009 |
Signing of Amended & Restated WUA |
27th October 2009 |
Signing of Finance Documents |
05th November 2009 |
Financial Close |
December 2009 |
COD |
23rd March 2013 |