HABIBULLAH COASTAL POWER PROJECT

Salient Features

Company Habibullah Coastal Power (Pvt.) Company
Capacity 140 MW (Gross)
Location Quetta
Fuel Natural Gas
Technology Combined Cycle
Plant Configuration 3 Gas Turbines + 1 Steam Turbines
Power Purchaser WAPDA
Fuel Supplier SSGC
Term of the PPA 30 Years
Registered Address Habibullah Coastal Power (Private) Company C-18, Block 4, Clifton Karachi
Email hcpc@eptp.com.pk

Important Milestones

Submission of Application June 28, 1994
Issuance of Letter of Interest (LOI) June 14, 1994
Issuance of Letter of Support (LOS) July 31, 1994
Date of Financial Closing April 04, 1996
Commissioning Date September 11, 1999
Net / Dependable Capacity 126 MW

Contractual Agreements

Implementation Agreement (IA) March 20, 1996
Power Purchase Agreement (PPA) March 25, 1996
Gas Supply Agreement (GSA) February 28, 1996
Amendment in the GSA March 31, 1996
GOP Guarantee May 9, 1996