QUAID-E-AZAM THERMAL POWER PROJECT

Salient Features

Project Company Quaid-e-Azam Thermal Power Ltd. (QATPL)
Main Sponsor Government of Punjab
Location Bhikki, district Sheikhupura, Punjab
Gross Capacity 1180.13MW (at RSC)
Net Capacity 1156.675MW (at RSC)
Technology Combined Cycle Gas Turbine (GE H Class - 9HA.01 CCGT) (Multi-Shaft)
Configration 2GT+2HRSG+1ST
Total Project Price(USD) 769.976Million
Debt Equity Ratio 75% Debt & 25% Equity
Power Purchaser CPPA-G
Primary Fuel R-LNG
Secondary Fuel HSD
Fuel Supplier SNGPL
Net Efficiency 61.59%

Important Events

Submission of Proposal 24-JUN-2015
Approval of PPIB Board 14-MAR-2016
Issuance of Notice to Proceed 06-JUL-2015
Issuance of LOI 13-JUL-2015
Generation License Application 15-JUL-2016
Tariff Determination 14-APR-2016
Date of issuance of LOS 09-MAY-2016
Implementaion Agreement 16-AUG-2016
Power Purchase Agreement 22-JUL-2016
Fuel Supply Agreement 22-JUL-2016
Achievement of Financial Close 22-AUG-2016
Partial Commissioning 1 17-JUN-2017 GT-1 Commissioning
Partial Commissioning 2 08-MAY-2017 GT-2 Commissioning
COD 20-May-2018