Important Milestones |
|
Submission of
Application
|
24-09-2005 |
|
Issuance
of Letter of Interest (LOI)
|
Not Applicable |
|
Issuance
of Letter of Support (LOS) |
07-04-2007 |
|
Date of
Financial Closing |
14-11-2007 |
|
Commissioning Date |
18-12-2009 |
|
Net
/ Dependable Capacity |
214 MW |
|
Contractual Agreements |
|
Implementation Agreement |
18-09-2007 |
|
Power Purchase Agreement (PPA)
|
06-09-2007 |
|
Fuel
Supply Agreement (FSA) |
07-10-2007 |
|
GOP
Guarantee
|
14-11-2007 |