tapal energy power project
|
|
|
 |
|
Salient Features |
|
Company |
Tapal Energy (Pvt.) Limited |
|
Capacity |
126 MW (Gross) |
|
Location |
District West, Karachi |
|
Fuel |
Furnace Oil |
|
Technology |
Diesel Engines |
|
Plant Configuration |
12 Oil Fired Engines |
|
Power
Purchaser
|
KESC |
|
Fuel
Supplier |
PSO |
|
Term
of the PPA |
22 Years |
|
Registered Address |
Tapal
Energy Limited
F-25,
Block 5, Kehkashan, Clifton
Karachi. |
|
Email |
telcoff@tapalenergy.com.pk |
|
|
Important Milestones |
|
Submission of Application |
June 16, 1994 |
|
Issuance of Letter of Interest (LOI) |
June 28, 1994 |
|
Issuance
of Letter of Support (LOS) |
September 18, 1994 |
|
Date of
Financial Closing |
March 11, 1996 |
|
Commissioning Date |
June 20, 1997 |
|
Initial Dependable Capacity |
119.5 MW |
|
Contractual Agreements |
|
Implementation Agreement (IA) |
August 8, 1994 |
|
Power
Purchase Agreement (PPA)
|
September 26, 1995 |
|
Fuel Supply Agreement (FSA) |
March 7, 1996 |
|
GOP Guarantee |
April 18, 1996 |
|
| |
|
|
|