Southern Electric Power Project
|
|
|
 |
|
Salient Features |
|
Company |
Southern Electric Power
Project |
|
Capacity |
115.2 MW (Gross) |
|
Location |
Raiwind, Lahore |
|
Fuel |
Residual Fuel Oil (RFO) |
|
Technology |
Diesel Engines |
|
Plant Configuration |
5 Units |
|
Power
Purchaser
|
WAPDA |
|
Fuel
Supplier |
PSO |
|
Term
of the PPA |
30 Years |
|
Registered Address |
Southern Electric Power Co. Ltd.
90-West, 6th Floor
Razia
Sharif Plaza, Blue Area
Islamabad. |
|
Email |
info@sepcol.com |
|
|
Important Milestones |
|
Submission of Application |
June 12, 1994 |
|
Issuance of Letter of Interest (LOI) |
June 28, 1994 |
|
Issuance
of Letter of Support (LOS) |
August 3, 1994 |
|
Date of
Financial Closing |
October 25, 1995 |
|
Commissioning Date |
July 12, 1999 |
|
Initial Dependable Capacity |
112.1 MW |
|
Contractual Agreements |
|
Implementation Agreement (IA) |
November 23, 1994 |
|
Supplement No. 1 |
March 7, 1994 |
|
Power
Purchase Agreement (PPA)
|
November 17, 1994 |
|
Amendment No. 1 |
October 25, 1995 |
|
Fuel Supply Agreement (FSA) |
November 30, 1994 |
|
Amendment No. 1 |
October 24,1995 |
|
GOP Guarantee |
August 26, 1996 |
|
Cost Overruns |
Yes |
|
| |
|
|
| |
|
|
|