SABA POWER PROJECT
|
|
|
 |
|
Salient Features |
|
Company |
Saba Power Company |
|
Capacity |
114 MW (Gross) |
|
Location |
Farouqabad, Shiekhupura, Punjab |
|
Fuel |
Residual Fuel Oil (RFO) |
|
Technology
|
Steam Turbines |
|
Plant Configuration |
One Furnace Oil Fired Unit |
|
Power
Purchaser
|
WAPDA |
|
Fuel
Supplier |
PSO |
|
Term
of the PPA |
30 Years |
|
Registered Address |
El
Paso Technology Pakistan (Pvt) Limited
Saba
Power Company Limited
3rd
Floor, G. D. Arcade
73-E,
Fazal-ul-Haq Road
Islamabad. |
|
Email |
Nasir.chishti@elpaso.com |
|
|
Important Milestones |
|
Submission of Application |
June 20, 1994 |
|
Issuance
of Letter of Interest (LOI)
|
June 28,
1994 |
|
Issuance
of Letter of Support (LOS) |
September 18, 1994 |
|
Date of
Financial Closing |
April 3,
1996 |
|
Commissioning Date |
December 31, 1999 |
|
Net
/ Dependable Capacity |
125 MW |
|
Contractual Agreements |
|
Implementation Agreement (IA) |
March 31, 1996 |
|
Power
Purchase Agreement (PPA)
|
December 26, 1994 |
|
Amendment No. 1 |
August 8, 1996 |
|
Fuel Supply Agreement (FSA) |
April 9, 1995 |
|
GOP Guarantee |
August 26, 1996 |
|
| |
|
|
| |
|
|
|