HUB POWER PROJECT
|
|
|
 |
|
Salient Features |
|
Company |
Hub Power Company |
|
Capacity |
1292 MW (Gross) |
|
Location |
Tehsil Hub, District Lasbela, Balochistan |
|
Fuel |
Residual Furnace Oil (RFO) |
|
Technology
|
Oil Fired, Steam Turbines |
|
Plant
Configuration
|
4x323 MW Steam Turbines |
|
Power
Purchaser |
WAPDA |
|
Fuel
Supplier |
PSO |
|
Term
of the PPA |
30 Years |
|
Registered Address |
Hub Power Company
Limited
Islamic Chamber
Building
Block-9, Clifton
Karachi. |
|
Email |
info@hubpower.com |
|
|
Important Milestones |
|
Submission of Application |
January, 1988 |
|
Issuance
of Letter of Interest (LOI)
|
April 27,
1994 |
|
Issuance
of Letter of Support (LOS) |
None |
|
Date of
Financial Closing |
January
26, 1995 |
|
Commissioning Date |
March 31, 1997 |
|
Capacity |
1299 MW |
|
Contractual Agreements |
|
Implementation Agreement (IA) |
August 3, 1992 |
|
Power
Purchase Agreement (PPA)
|
August 3, 1992 |
|
Gas Supply Agreement (GSA) |
August 3,
1992 |
|
GOP Guarantee |
January 3, 1995 |
|
Settlement Agreement |
December 17, 2000 |
|
Settlement Amended Agreement |
October 14, 2001 |
|
|