|
1 |
What does IPP stands for
?
IPP is an abbreviation of
Independent Power Producer.
Top |
|
2 |
How many projects in the
private sector are in operation in Pakistan ?
At present there are 16
private power projects with a capacity of above 5500 MW which are in
operation. This is roughly one-third of the total power generation capacity
of Pakistan.
Top |
|
3 |
Why has private sector
been inducted in power generation ?
Power shortage had been one
of the chronic problems hampering Pakistan’s socio-economic growth By 1994,
the problem had assumed such acute dimensions that power supply fell short
of demand by almost 2000 MW during peak load hours. On a routine basis, this
resulted in forced interruptions in the supply of electricity to consumers
during peak hours resulting in load shedding. The unreliable power supply
shattered the industrial progress. There was a gap between demand and supply
due the rapid increase in electricity demand (estimated to be growing at a
rate of 7-8 % per annum at that time).
This situation called for immediate intervention by the GOP
through adoption of policy measures aimed at massive resource mobilization
for investment in the power/energy sector. The enormous quantum of required
investment compared with the constrained funding potential of the national
exchequer, was not conducive to allocation of scarce GOP funds for energy.
Therefore, the GOP took a bold initiative to encourage private sector
investment in infrastructure development, in the power sector.
Top |
|
4 |
Why did the 1994 Power
Policy receive such an enthusiastic response ?
In March 1994, the GOP announced the Private Power Policy
1994 which, essentially, comprised a well-thought-out package of incentives
to attract foreign direct investment (FDI) in private power generation
projects, due to which the Policy received a very enthusiastic response. The
package of incentives envisaged in the 1994 Power Policy was internationally
competitive in terms of assured cash flow for debt repayment and returns on
investment. Procedures were simplified; PPIB was created as a one window
facility to eliminate unnecessary delays in finalization and approval of
projects and to facilitate interaction between the GOP and investors; local
currency investment requirements were reduced; and measures were adopted to
create and encourage a domestic corporate debt security market.
Top |
|
5 |
Who are the main lenders
to IPPs in Pakistan ?
The main lenders to IPPs in Pakistan are World Bank, Asian
Development Bank, International Finance Co-operation, US-Exim Bank, J-Exim
Bank etc.
|
|
6 |
What is the minimum
equity requirement to finance IPPs in Pakistan ?
The minimum equity requirement to finance IPPs in Pakistan is
20%.
Top |
|
7 |
Why IPPs were allowed to
do business in Pakistan ?
If projects are implemented
through the public sector utilities, they absorb a significant portion of
national budget allocation. The allocation for new power projects surpasses
the cumulative allocation for health, housing, education and agriculture
sectors. Therefore, in order to save governmental allocations for these
vital sectors, private sector investment has been sought in Pakistan.
|
|
8 |
IPPs have resulted in
sky-rocketing tariff. The consumer tariff and electricity has become
unaffordable, Is it true ?
Although after induction of IPPs the consumer tariff has been
increased, but only IPPs can not be blamed. The price hike is mainly due to
the increase in the furnace oil prices. Secondly, the electricity generated
through IPPs will dip down sharply after completion of debt servicing
period. The consumers will get the real benefit of IPPs at that time. The
Bulk Power Tariff (BPT) offered by Pakistan was comparable to the IPP tariff
in other Asian countries. As per a research conducted by a famous
international firm the BPT was the third lowest amongst the list of fourteen
IPPs of some other countries of the Asian region.
Top |
|
9 |
Environment for IPPs is
hostile. Are the investors expected to invest further in the business of
IPPs ?
Environment for IPPs is NOT at all hostile. The initial
turbulent period has passed. The misgivings and hostilities which occurred
during the teething time and which were the result of inexperience on both
sides of the fence i.e. IPPs and the Government, have now been overcome. Now
there is a new rapprochement between the Government and the investors. The
investors are very eagerly looking forward to invest in Pakistan. Infact,
pursuant to the announcement of the Power Policy 2002, a very encouraging
response has been received from the investors.
Top |
|
10 |
The 1994 power policy
resulted in induction of only RFO based thermal power plants. Reasons ?
Hydel projects are more capital intensive than the thermal
projects. Although the Policy-1994 promises more tariff for the hydel
projects but still due to their capital-cum-time intensiveness and
hydrological risks, hydel projects could not be materialized. Thus thermal
projects which could start generating the electricity in shortest possible
time, and which are less time consuming for installation rushed to fill the
vacuum.
Top |
|
11 |
Thermal power plants
using furnace oil are depriving the country of hard earned foreign exchange.
What steps the Government has initiated to check this ?
Conscious of this fact, the Government is exploring the
avenues of transforming the thermal projects from furnace oil to gas. Almost
all the public sector projects which do have useful lives and which have the
appropriate technology have been converted to dual fired mode, and they
consume gas as per the availability in system. Under the Power Policy for
Power Generation 2002, indigenous resources like hydel and coal are being
encouraged.
Top |
|
12 |
Coal is abundantly
available in Pakistan. Why this coal is not being utilized ?
To develop coal resources of
Pakistan serious efforts are afoot. A task force under the President of
Pakistan is rigorously following a plan to fully exploit the coal resources
especially the Thar Coal reserves. Sindh Government and PPIB are also in
good liaison to develop coal resources. Many MOUs signed in this regard
promise a bright future for the brown coal.
Top |